You are here

Feed aggregator

Next-Stage C4ISR Bandwidth: The AEHF Satellite Program

Defense Industry Daily - Fri, 22/05/2015 - 02:01
AEHF concept
(click to view full)

The USA’s new Advanced Extremely High Frequency (AEHF) satellites will support twice as many tactical networks as the current Milstar II satellites, while providing 10-12 times the bandwidth capacity and 6 times the data rate transfer speed. With the cancellation of the higher-capacity TSAT program, AEHF will form the secure, hardened backbone of the Pentagon’s future Military Satellite Communications (MILSATCOM) architecture, with a mission set that includes nuclear command and control. Its companion Family of Advanced Beyond-line-of-sight Terminals (FAB-T) program will give the US military more modern, higher-bandwidth receiving capabilities, and add more flexibility on the front lines. The program has international components, and partners currently include Britain, Canada, and the Netherlands.

This article offers a look at the AEHF system’s rationale and capabilities, while offering insight into some of the program’s problems, and an updated timeline covering over $5 billion worth of contracts since the program’s inception.

The AEHF Program Program Status and Budgets

The decline in GAO program coverage creates some challenges in making apples to apples comparisons, but the trends are clear. Like a number of American satellite development programs, AEHF has been cited for cost overruns and schedule slips. Part of the reason involves the US National Security Agency’s failure to furnish key cryptography requirements and specifications, and mechanical and construction difficulties were also involved.

Yo-yoing constellation size played a role of its own in program total changes, while creating cost spikes for individual satellites. Satellites 5 & 6 are expected to cost almost double the average for SV 1-3, owing to a production line that was interrupted and restarted because the decisions to add more satellites came after a gap of 4 years. That was too late to keep the production line from closing temporarily, and re-starts are difficult and expensive.

Note that USAF budgets do not include the US Army’s small participation, contributions from international partners, or RDT&E funding beyond FY 2014:

Past and Future C4ISR Future?
(click to expand)

The AEHF partnership program currently involves 4 operational and 2 reserve satellites, and includes Britain, Canada, and the Netherlands.

AEHF began as a program in April 1999, and development began in September 2001. The production decision was made in June 2004, and the original intent was to launch the first satellite in late 2007. NSA delays in providing key cryptographic requirements ended up being very expensive, and other technical difficulties also pushed the program back. First launch didn’t take place until August 2010.

Along the way, the AEHF program’s size has yo-yoed. In December 2002, optional satellites 4 and 5 were deleted from the program, with the intention of making AEHF only an interim bridge to the larger Transformational Satellite Network (T-SAT) and its ultra-high bandwidth laser interlinks. As TSAT faltered, however, the AEHF bridge became the destination.

The first indication of shifts in the program came when the Pentagon’s April 2008 Selected Acquisition Reports confirmed that the program had expanded to add AEHF-4. The TSAT successor program was restructured, but in June 2009, Secretary of Defense Gates finally lowered the boom and confirmed that the Pentagon intended to kill TSAT, leaving Advanced EHF satellites as the military’s main future guarantors of secure, hardened bandwidth. In response, the US military expanded and internationalized the Wideband Global SATCOM (WGS), restored AEHF SV-5 to the hardened constellation, and eventually added a 6th AEHF satellite in April 2010.

The 5th and 6th satellites are currently planned as a reserve that will replace the first 2. Even so, the USAF is considering a 7th and 8th satellite, as it works through an Analysis of Alternatives for its “Resilient Basis for SATCOM (RBS) in Joint Operations” study. The exact nature of the AEHF Follow-On will be informed by this protected MILSATCOM AoA.

Down here on Earth, the companion FAB-T (Family of Advanced Beyond-line-of-sight Terminals) development effort aimed to create a family of software-defined radios that could become a common terminal for the next generation of High Data Satellite Communications, including AEHF, Wideband Gapfiller, and other future satellite systems. It’s aimed at aircraft, and the NSA’s poor handling of its cryptographic challenges has contributed to the overall program’s delays and cost overruns. A limited production contract is expected by mid-2014.

Beyond Boeing’s FAB-T, a number of vendors are developing and fielding SATCOM solutions that are compatible with AEHF, for use by land and naval assets.

Launch Plans and Dates The Process
click for video

AEHF Space Vehicle-1 (SV-1) launched in August 2010, almost 3 years later than originally planned, but slightly earlier than some 2010 reports had expected. It encountered serious propulsion problems, which left it well short of its operational orbit, but ground control found some timely workarounds the eventually got the satellite to its orbital plane. The flip side is that instead of conducting on-orbit testing in August 2010, the USAF had to wait until November 2011. Meanwhile, AEHF SV-2 and SV-3 were ready, but SV-1’s technical failure and delayed on-orbit tests left them on hold.

AEHF SV-2 was slated for launch in May 2011, but was eventually launched on May 4/12.

AEHF SV-3 missed its January 2012 window. A full launch schedule meant that the launch ended up taking place on Sept 18/13.

AEHF SV-4 is still expected to launch in Q3 (spring) FY 2017, which tracks with the 4-year delay before the additional order.

SV-5 was supposed to follow in 2018, and SV-6 in 2020, but they’ve been shifted to a reserve role instead. Despite the US military’s exploding demand for bandwidth, they’ll be used as end-of-life replacements for SV-1 and SV-2, or as an emergency replacement option for any AEHF satellite that malfunctions or is destroyed.

The AEHF Satellites

Advanced EHF satellites will provide at least 10 times greater total capacity, and offer channel data rates 6 times higher, than current Milstar II communications satellites. These new hardened and crosslinked satellites are designed to be very hard to jam, while surviving shocks that can include EMP radiation surges from atmospheric nuclear blasts. They’ll offer 24-hour low, medium, and high data rate satellite connectivity from 65 N to 65 S latitude, worldwide.

Each Advanced EHF satellite employs more than 50 communications channels via multiple, simultaneous downlinks. To accomplish their goal of 10x capacity and 6x channel data of existing Milstar II satellites, Advanced EHF adds new higher data-rate transmission modes:

Each satellite uses than 800 ASICs (chips) delivered by Honeywell Aerospace in Plymouth, MN, and BAE Systems of Arlington, VA. These customized chips benefit from general advances in chip density and speed since the existing MILSTAR constellation was built, which means reduced weight. Each AEHF payload includes:

  • 25 computers
  • Almost 1 million lines of software code
  • 70 unique monolithic microwave integrated circuit (MMIC) chip designs – almost 18,000 total MMICs
  • More than 50 unique integrated microwave assemblies and hybrid designs – over 13,000 total.

AEHF is X-band capable for high-bandwidth data rates, in addition to the Milstar low data rate and medium data rate modes that ensure backward compatibility. The crosslinks eliminate the need to route messages via terrestrial systems, which cuts some of the latency associated with satellite links.

Bandwidth is already a significant constraint in theater, and these higher data rates will allow more transmission of tactical military communications into remote areas, to include real-time video, battlefield maps, and targeting data.

The AEHF Satellites: Contracts & Key Events Payload testing
(click to view full)

The Pentagon DefenseLINK summaries of awarded AEHF contracts were unusually informative, providing a commendable level of insight into the program and its challenges. Note, especially, the effects of key delays from NSA re: cryptography in the early years. We’ve also broken out the AEHF’s FAB-T terminals that will connect the military to the AEHF network and other satellites. Though the satellites and terminals are intertwined on many levels, and some cryptography-related contracts may mention neither but apply to both, separation of these contracts adds more clarity.

As of January 2013, Lockheed Martin is under contract for 6 satellites.

Unless otherwise specified, the USAF Headquarters Space and Missile Systems Center in Los Angeles, CA has issued the following requisitions under contract #F04701-02-C-0002:

Satellites FY 2014 – 2015

SV-4 launch prep. NGC on AEHF

May 22/15: Lockheed Martin has been awarded a $735 million support contract for the Air Force’s Advanced Extremely High Frequency Satellites, Milstar and Defense Satellite Communications System III. The company was awarded a similar contract for the latter two in 2009.

Dec 27/13: SV-4 launch prep. Lockheed Martin Space Systems Co., Sunnyvale, CA receives a $116.1 million cost-plus-incentive-fee contract modification for AEHF SV-4 (q.v. Dec 15/10) launch operations, including support to integrate the satellite into the launch rocket. Launch preparation activities begin at launch minus 12 months, and include an early orbit operations rehearsal campaign alongside the physical preparations.

$2 million in USAF FY 2014 missile procurement funds are committed immediately. Work will be performed at Sunnyvale, CA, and El Segundo, CA, and is expected to be complete July 31/19. The USAF Space and Missile Systems Center, PKJ, Los Angeles Air Force Base, CA, is the contracting activity (F04701-02-C-0002, PO 0548).

Satellites FY 2013

SV-5 & SV-6; SAR is sort of good news; Canada begins using AEHF. Encapsulation
(click to view full)

Sept 18/13: AEHF-3 launch. A Delta V 531 rocket blasts off from Cape Canaveral, and successfully launches AEHF-3. The satellite will spend the next 110 days thrusting to raise its orbit, followed by about 60 days of on-orbit testing. It’s ULA’s 40th mission with the Atlas V EELV.

AEHF-3 was encapsulated in its 5m diameter fairing on Sept 11/13. Sources: ULA | USAF Los Angeles AFB | Lockheed Martin.

AEHF-3 launched

Sept 16/13: IOC Delay. Inside Defense Reports that the USAF is citing Software Development Difficulties as the reason for delaying AEHF’s Initial Operational Capability designation by a year. Source: Inside Defense, “Air Force Delays Key AEHF Milestone One Year, Citing Software Development Difficulties”.

IOC delayed

Sept 12/13: Netherlands. Lockheed Martin reveals that in July 2013, the Dutch tested engaging AEHF-1 and AEHF-2, exchanging voice and data communications with the U.S. and Canada by connecting to the AEHF-2 satellite, crosslinking with AEHF-1, then downlinking to the U.S. Navy terminal in San Diego and a Canadian terminal at Shirley’s Bay, Ontario. They also completed their first local AEHF call from ship to shore, using international versions of the Navy Multi-Band and SMART-T terminals. Source: Lockheed Martin, Sept 12/13 release.

June 20/13: Canada. A U.S.-Canada team has successfully communicated with the USAF’s 4th Space Operations Squadron at Schriever Air Force Base, CO, using AEHF-1 satellite and a SMART-T terminal variant to exchange data from a location near Ottawa, Canada. Follow-on tests involved multiple Navy Multi-Band IP variant terminals exchanging data over AEHF networks.

Canada is the 1st international partner to reach this point, and will continue testing for several months as their forces move toward initial operational capability. Britain and the Netherlands are scheduled to complete their first terminal connections by the end of 2013. Lockheed Martin.

May 24/13: SAR. The Pentagon finally releases its Dec 31/12 Selected Acquisitions Report [PDF], and AEHF is a good news story. Not completely good news, given the raised costs for these satellites thanks to the production gap, but $500 million is always nice:

“Advanced Extremely High Frequency (AEHF) Satellite – The AEHF program is comprised of two subprograms, Space Vehicles 1-4 and Space Vehicles 5-6. Only the Space Vehicles 5-6 subprogram had selected cost changes in the December 2012 SAR. AEHF Space Vehicles 5-6 – Subprogram costs decreased $510.4 million (-14.6%) from $3,488.2 million to $2,977.8 million, due primarily to a reduced estimate to reflect program efficiencies for production and launch operations for Space Vehicles 5-6 (-$507.1 million). The savings were applied to higher Air Force needs.”

SAR: good news, sort of

April 10/13: FY 2014 Budget. The President releases a proposed budget at last, the latest in modern memory. The Senate and House were already working on budgets in his absence, but the Pentagon’s submission is actually important to proceedings going forward. See ongoing DID coverage.

For AEHF, the 2014 budget continues to reduce annual funding through FY 2017, but the block buy of SV-5 and SV-6 is on track. That budget is $2.59 billion maximum, based on $227 million in FY 2011 for long lead time parts, an unfinalized contract with a $2.199 billion maximum for production and launch, and $164 million for potential Engineering Change Orders (ECOs).

There are a few important changes, beginning with having SV-5 and SV-6 “replace AEHF-1 and AEHF-2 at the end of their useful life,” instead of launching to address the US military’s exploding demand for bandwidth. The program has also extended. Instead of terminating in 2018, the budget suddenly adds advance procurement in FY 2016 – 2017, and a big FY 2018 spike for 2 clones of SV-5/6. AEHF SV-7 and SV-8 are really just placeholders so far, as the USAF works through an Analysis of Alternatives for its Resilient Basis for SATCOM (RBS) in Joint Operations study. The exact nature of the AEHF Follow-On will be informed by the protected MILSATCOM AoA.

Jan 3/13: SV-5/6. Lockheed Martin Space Systems Co., Sunnyvale, CA receives a $1.937 billion contract modification for AEHF Space Vehicle 5 and 6 “Production Launch Operations.” When we add ancillary and long-lead item contracts announced to date, the total so far for SV-5 and SV-6 comes to $2,469.2 million, or about $1.235 billion per satellite:

  • Jan 3/13: $1,936.5 (main)
  • Sept 17/12: $43.0 (crypto)
  • June 25/12: $249.0 (antennas)
  • May 10/12: $13.5 (parts)
  • Dec 5/11: $167.2 (long-lead)
  • Nov 16/11: $60.0 (long-lead)

As noted above, the need for a production line restart created a huge cost increase. Work will be performed in Sunnyvale and El Segundo, CA, and is expected to be complete by Jan 24/22. Note that substantially the same announcement was made on Dec 28/12 (FA8808-12-C-0010).

SV-5 & SV-6 main contract

Satellites FY 2012

AEHF-1 and 2. AEHF-2 launch
(click for video)

Sept 24/12: AEHF-2 ready. The satellite completes its on-orbit testing successfully. Testing began with single-satellite testing, followed by a period of crosslink testing between AEHF-1 and AEHF-2, and culminating with testing in the operational Milstar constellation. USAF.

Sept 17/12: SV-5/6. Lockheed Martin Space Systems in Sunnyvale, CA receives a $43 million contract modification for AEHF SV-6 Crypto Availability KI-54D. Decoded, that means they’ll produce/order and then install the satellite’s “black box” encoding/ decoding module for secure communications.

Work will be performed Camden, NJ and El Segundo, CA (Northrop Grumman, sub-contractor), and is expected to be complete by Oct 16/15 (F04701-02-C-0002, PO 0544).

Aug 10/12: AEHF-2 on-orbit. AEHF-2 arrives at its geostationary orbit test location and altitude. Unlike AEHF-1, this one went smoothly: 4 Liquid Apogee Engine burns to get above the densest Van Allen radiation belts, deployment of the solar arrays, then 47 Hall Current Thruster burns over an 85-day period. Payload activation and about 2 months of on-orbit testing are next. USAF.

June 25/12: SV-5/6. Lockheed Martin in Sunnyvale, CA receives a $249 million firm-fixed-price contract for AEHF SV-5 and SV-6 antennas and flight materials. That kind of hardened bandwidth in space doesn’t come cheap. Work will be performed in Sunnyvale, CA, and will be complete by Nov 1/12 (FA8808-12-C-0010, PO 0001).

May 10/12: SV-5/6. Lockheed Martin Space Systems in Sunnyvale, CA receives a $13.5 million firm-fixed-price contract for Space Vehicle 5/6 production. Specifically, they’ll supply a gimbal mechanism and beam select switch parts.

Discussion with Lockheed Martin confirms that this is for AEHF. Work will be performed in Sunnyvale, CA until Dec 30/13 (FA8808-12-C-0010).

Feb 27/12 – May 4/12: AEHF-2 delivery & launch. Lockheed Martin delivers AEHF-2 to the Air Force on Feb 27/12, after keeping it in storage since the end of 2010. The satellite was scheduled for launch on April 27/12 from Cape Canaveral, using an Atlas V rocket. Encapsulation took place on April 21/12 at the Astrotech Space Operations facility in Titusville, FL, but the launch date slipped to May 4/12.

The launched from Cape Canaveral Air Force Station was successful. AEHF SV-2 will take about 110 days to fly to its final orbit, followed by about 120 days of on-orbit testing, before it is transferred to the 14th Air Force for Satellite Control Authority. USAF | ULA | Lockheed Martin | Dutch MvD [in Dutch].

AEHF-2 launch

Dec 5/11: SV-5/6 lead-in. Lockheed Martin Space Systems Corp. in Sunnyvale, CA receives a $167.2 million firm-fixed-price and cost-plus-incentive-fee contract modification, to buy more AEHF SV-5 & SV-6 long lead time materials. This comes on top of the $60 million Nov 16/11 announcement, and includes the basic long-lead parts for Lockheed Martin’s electronic boxes and core structure, and for Northrop Grumman’s payload. These parts have a 24-week (about 6 month) lead time, and will support the coming SV 5/6 production contract.

Work will be performed in Sunnyvale, CA (F04701-02-C-0002, PO 0528).

Dec 2/11: Support. Lockheed Martin Space Systems Corp. in Sunnyvale, CA receives a $312.2 million cost-plus-incentive-fee contract modification for AEHF satellite program engineering support from Dec 1/11 to Dec 31/14.

Work will be performed at Redondo Beach, CA, and could include “on-orbit anomaly resolution and investigation” (vid. AEHF-1’s tribulations), flight and payload software sustainment after on-orbit tests are done, Networked AEHF System Tested tool sustainment, mission control familiarization, and development test. They’ll also provide hardware, software, training and logistics support, technical order maintenance, system security and information assurance engineering, support for AEHF and Milstar combined constellation integration transition and test activities, coordination with the Milstar O&M contractor, satellite database updates for Milstar and AEHF, and on-site technical support for satellite operations at Schriever AFB, CO, and Vandenberg AFB, CA. The USAF Space and Missile Systems Center’s Military Satellite Communications Systems Directorate in Los Angeles, CA manages the contract (F04701-02-C-0002, PO 0454).

Nov 16/11: SV-5/6 lead-in. Lockheed Martin Space Systems in Sunnyvale, CA received a $60 million firm-fixed-price and cost-plus-award-fee contract modification for AEHF SV-5 & SV-6 long lead time materials. The USAF Space and Missile Systems Center’s Military Satellite Communications Systems Directorate in El Segundo, CA manages the contract (F04701-02-C-002, PO 0525).

Nov 3/11: AEHF-1. The USAF announces that AEHF SV-1 has completed initial activation of its communications payload, and has begun on-orbit testing. This included successful deployment of the payload wings, the Gimbal Dish antennas, and the Advanced Anti-Jam Nulling antennas, as well as log-ons and data communications using communication terminals located at Schriever AFB, CO, and M.I.T/Lincoln Labs, MA.

A combined team of Air Force, Aerospace Corp., Lockheed Martin, and Northrop Grumman personnel have worked on activation, and SMC MILSATCOM Systems Director Dave Madden believes that by the end of November, they’ll have enough data to make a decision on whether or not to launch AEHF SV-2 in April 2012.

Oct 25/11: The USAF announces that AEHF-1 has finally reached its designated orbital slot, 14 months after launch. The process required approximately 500 thruster burns, but they still expect to get the required 14 years of mission life from the satellite, even though onboard fuel is directly correlated with mission life. Other US satellites have lasted longer than expected in orbit, so it’s hard to evaluate the USAF’s expectation without knowing the before/after confidence intervals, safety margins, etc. Time will tell.

The next step is a 4-month detailed test and checkout phase of all spacecraft systems, which is actually the most critical on-orbit phase. If the satellite’s other systems are performing as expected, the Space and Missile Systems Center plans to transfer satellite command authority to USAF Space Command’s 14th Air Force in early 2012. USAF.

Huge save: AEHF-1 makes it!

Oct 4/11: AEHF-1. The Space & Missile systems Center at Los Angeles AFB says that AEHF-1 is going to be a bit late to its orbital slot. It will arrive in late October instead of today, “while maintaining the safety of the vehicle and conserving on-board fuel.” Burning the Hall Current Thrusters to make up for the Liquid Apogee engine’s problems has a price, as fuel is the main determinant of satellite lifespan in orbit. The MILSATCOM Systems Directorate says that when they achieve the desired orbit, AEHF-1 will maintain the same expected capabilities they were estimating back in June.

Satellites FY 2011

AEHF-1 not where it should be. SV-4. Cost increases; layoffs. AEHF-1 recovery award
(click for video)

Sept 30/11: Support. Lockheed Martin Space Systems Corp. in Sunnyvale, CA received a $9.8 million cost plus award fee contract modification to extend AEHF sustaining engineering support by 2 more months, from Sept 30/11 through Nov 20/11. Support is provided for MilStar and AEHF satellite operations at Schriever Air Force Base, CO and Vandenberg Air Force Base, CA, and includes on-orbit anomaly resolution and investigation, flight and payload software sustainment, Networked AEHF System Tested Tool sustainment, support for mission control segment Increment 5 familiarization and development test, mission control segment Increments 4 and 5 software maintenance, and on-site technical support.

The USAF Missile Systems Center Military Satellite Communications Systems Directorate in El Segundo, CA manages the contract (F04701-02-C-0002, PO 0519).

June 14/11: Layoffs. Layoffs at Lockheed Martin Space Systems. This branch of the firm employs around 16,000 employees in 12 states, but intends to shed 1,200 employees by year-end, including a 25% cut in middle management to reduce impacts elsewhere. LMSS’ Sunnyvale, CA; Pennsylvania; and Denver, CO sites will be hardest hit, and the firm’s release says that it’s pushed in part by several of their major programs moving beyond the labor-intensive development phase.

Space Systems says it will offer “eligible” salaried employees an opportunity for a voluntary layoff, plus career transition support for all affected employees. Lockheed Martin.

Layoffs

June 13/11: Studies. Lockheed Martin Space Systems in Sunnyvale, CA receives a $17.7 million cost-plus-award-fee contract modification, extending AEHF’s capabilities insertion study. As Lockheed Martin’s engineers contemplate ways to improve future AEHF satellites and meet growing military bandwidth needs, they will be performing capability/requirements tradeoffs for systems, technology assessments, development of design alternatives, risk assessments, and cost and schedule analysis (F04701-02-C-0002, PO 0500).

May 9/11: Changes. Lockheed Martin Corp. in Sunnyvale, CA receives a $21.3 million cost-plus-award-fee contract modification to develop AEHF program software changes in 3 areas. Absent further specifics, the award has been placed in this section.

Work will be performed in Sunnyvale, CA, and King of Prussia, PA. At this point, $19 million has been committed by the USAF Space and Missiles Center, SMC/PKJ in El Segundo, CA (F04701-02-C-0002, P00483).

April 15/11: The Pentagon’s Selected Acquisitions Report ending Dec 30/10 includes the “significant cost changes” in AEHF program – both satellites and terminals. The satellite section reads:

“Program costs increased $1,065.1 million (+8.6 percent) from $12,448.9 million to $13,514.0 million, due primarily to a revised procurement estimate to fully fund the fifth and sixth satellites (+$1,620.7 million) and an extension of interim contract support due to the launch delay for the first satellite (+214.5 million). These increases are partially offset by an estimating decrease due to an acquisition strategy change from full funding to a block buy for the fifth and sixth satellites (-$798.5 million).”

SAR – cost increases

April 7/11: AEHF-1. The USAF’s Space and Missile systems Center provides an update on AEHF-1 progress, as they work to move it into an operational orbit after it fell short upon launch. Today, AEHF-1 crosses the 20,000 km/ 12,427 mile perigee mark.

SMC says orbit-raising is successfully continuing as planned. Phases 1 & 2 using hydrazine thruster phase are complete, and the satellite is now using its AEHF’s Hall Current Thruster electric propulsion system. The goal is to reach geosynchronous orbit in late summer 2011. If they do, it would cap as remarkable effort, and a very nice recovery for the joint government and contractor team. On the other hand, fuel reserves are the #1 determinant of how long a geosynchronous satellite can remain effective, and AEHF-1’s fuel reserves will be much lower than planned. See also Nov 16/10 entry for more details. USAF SMC (no URL).

March 22/11: AEHF-1. AEHF-1 crosses the half-way mark to geosynchronous orbit, with its perigee climbing above 17,893 km/ 11,174 miles altitude. USAF SMC (no URL).

Dec 15/10: SV-4. Lockheed Martin Space Systems Co. in Sunnyvale, CA received a $1.31 billion contract modification for SV4, the 4th AEHF satellite, SV4 unique systems engineering, a system level factory test, system database management functions, systems level support equipment, and program management. At this time, $1.236 billion has been obligated (FO4701-02-C-0002; PO0448).

See also Sept 10/09 and July 18/06 entries, which raise total SV-4 contracts to $1.604 billion. USAF release.

SV-4 main contract

Dec 14/10: AEHF-1. In response to questions about AEHF-1’s orbital problems, the USAF Space and Missile Systems Center says they’ve briefed senior Air Force leaders, who are considering initiating a Safety Investigation Board. They will also present their investigation briefing to selected Congressional Staff Members later in December 2010. Based on the current costs for AEHF-1/2/3, the unit cost per satellite is about $1.7 billion, and the USAF is reviewing its options concerning contractor financial responsibility and/or penalties.

Under current plans, AEHF-1 is looking at a 9-month delay, reaching its test/check-out orbit on Aug 11/11, instead of Nov 10/10.

Nov 16/10: AEHF-1 may have launched successfully, but a propulsion system problem prevented a series of 3 liquid apogee engine burns, so it didn’t reach its operational mission orbit. Los Angeles AFB discusses the new plan to fix this, which involves 4 major stages:

The 1st Parking Burns stage used 3 of the 6 reaction engine assemblies, or REAs, to quickly raise the perigee altitude to reduce drag and attitude disturbances. The 5 pound thrusters brought the orbit to a perigee altitude of 1,156 km and an inclination of 19.9 degrees on Sept 7/10. Apogee altitude remained at 50,000 km, per plan.

The 2nd stage was a series of 6 REA Apogee Burns, to more efficiently raise the perigee path to 4,712 km, and lower inclination to 15 degrees. It was completed on Sept 22/10.

The 3rd stage involves firing 2 high-efficiency hall current thrusters (HCTs), for as long as 12 hours around the apogee altitude. These burns will continue every orbit, centered on apogee, and this stage is planned to last between 7-9 months. It began on Oct 20/10, with a 9 hour burn during AEHF-1’s 100th apogee. Meanwhile, the satellite has managed to deploy its solar arrays, and pass operational readiness checkouts.

The 4th and final stage will require a near-continuous firing of the HCTs to adjust to the final mission orbit, lasting about 3 months. Los Angeles AFB.

AEHF-1: We have a problem

Nov 9/10: Support Lockheed Martin Space Systems Co. in Sunnyvale, CA received a $49 million contract modification for AEHF sustainment engineering support from Oct 1/10 to Sept 30/11. At this point, $9 million has been committed by the AFSMC/MCSQ in El Segundo, CA (F04701-02-C-002; P00427).

Oct 28/10: Testing. Lockheed Martin announces the end of Intersegment System Testing (IST) for the 2nd AEHF satellite in Sunnyvale, CA, completing pre-launch verification for the new eXtended Data Rate (XDR) high-bandwidth service. XDR offers a 10-fold increase in system capacity, coverage and network connectivity, allowing applications such as real-time video, and voice and data conferencing. Completion of IST for AEHF-2 caps an extensive suite of interoperability tests with new XDR-capable user terminals, which demonstrating protected anti-jam communications at data rates up to 8 Mbps using agile satellite spot beams.

The 2nd AEHF satellite has completed all testing, and will be placed in storage in November 2010. The 3rd AEHF satellite is currently progressing through thermal vacuum environmental testing at the Lockheed Martin facility in Sunnyvale, CA.

Satellites FY 2010

AEHF-1 AEHF-1 highlights
(click for video)

Aug 16/10: Studies Lockheed Martin Space Systems Co. in Sunnyvale, CA received a $16 million contract to study AEHF enhancement options, and all funds have already been committed. With the demise of AEHF’s T-SAT successor, AEHF enhancements become a critical opportunity for the bandwidth-constrained US military (F04701-02-C-0002, P00443).

Aug 14/10: SV-1. The USAF’s 45th Space Wing launches AEHF-1 from Pad 41 in Cape Canaveral, FL, on board a United Launch Alliance Atlas V rocket. USAF | Dutch MvD | ULA | Lockheed Martin | Florida Today, incl. video | Spaceflight Now.

AEHF-1 launch

August 10/10: SV-1. AEHF-1 is encapsulated into the Atlas V rocket. The launch has been delayed again, until Aug 14/10.

July 16/10: SV-1. Los Angeles AFB announces that, the Lockheed-Martin/Air Force AEHF team has continued a long-standing tradition, and signed a piece of the flight thermal blanket for the AEHF-1 satellite in preparation for launch. The satellite was shipped on May 24/10, and is currently at Cape Canaveral Air Force Station, FL being readied for launch.

July 14/10: SV-1 launch slips. The USAF announces that:

“The Atlas V launch of the first Advanced Extremely High Frequency satellite from SLC-41 at the cape has been delayed 10 days from 30 July to 10 August. This delay was necessary to provide engineers more time to perform confidence testing on a launch vehicle component associated with releasing the fairing support structure. Processing on both the launch vehicle and satellite continues nominally to a new launch date of 10 August. This slip in the AEHF-1 launch is not expected to impact other launches in the manifest.”

See USAF | Lockheed Martin | United Launch Alliance | Florida Today, incl. video | Spaceflight Now.

May 25/10: SV-1. Lockheed Martin delivers the 1st new AEHF secure broadband communications satellite (SV-1) to the USAF, for a planned July 30/10 liftoff.

As of this date, Lockheed martin says that SV-2 has completed Final Integrated System Test, and is now preparing for Intersegment testing. SV-3 has now completed acoustic testing. Lockheed Martin.

AEHF-1 delivered.

April 14/10: Testing. Lockheed Martin announces that it has completed all factory testing of the first AEHF satellite, which means it’s ready for delivery to Cape Canaveral Air Force Station, FL for a September 2010 liftoff aboard an Atlas V rocket.

The 2nd AEHF satellite (SV-2) is in the midst of its final performance test known as Final Integrated System Test which will verify all spacecraft interfaces, demonstrate full functionality and evaluate satellite performance. The 3rd AEHF satellite, SV-3, is gearing up for acoustic testing.

April 1/10: The Pentagon releases its April 2010 Selected Acquisitions Report, covering major program changes up to December 2009. AEHF makes the list, owing to procurement shifts in the wake of TSAT’s cancellation:

“Program costs increased $2,510.3 million (+25.3%) from $9,938.6 million to $12,448.9 million, due primarily to a quantity increase of two satellites from four to six satellites (+$2,623.7 million). This increase was partially offset by decreases due to an adjustment to the cost estimate (-$20.0 million), Congressional general reductions (-$19.2 million), a contractor to civilian personnel conversion (-$11.8 million), and the application of revised escalation indices (-$53.9 million).”

SAR – to 6 satellites

March 30/10: GAO Report. The US GAO audit office delivers its 8th annual “Defense Acquisitions: Assessments of Selected Weapon Programs report. With respect to the AEHF, it’s a bit behind the curve in listing only 4 satellites in the program for its figures, but it does acknowledge them in its commentary. Excerpts include:

“The AEHF program has overcome the technical problems that have delayed the first satellite’s launch by almost 2 years and increased the cost of the program. Defective satellite parts were replaced and the satellite successfully completed system-level environmental testing… Three satellites have been added to the program in recent years… The cost of the fourth satellite is significantly more than the estimated $952 million (then-year dollars) cost of the third satellite because there is an estimated 4-year break in production and some electronics components are no longer manufactured. Program officials do not anticipate significant technical challenges, but integrating, testing, and requalifying the new components will require time and money… design specifications for the first three satellites will remain unchanged for satellites four through six, which will be clones except for obsolete parts. The program office estimates the cost of satellites five and six will be about $1.6 billion and $1.7 billion (then-year dollars), respectively, with estimated launch dates in 2018 and 2020.”

Oct 7/09: Studies. Lockheed Martin Space Systems in Sunnyvale, CA received a $21.6 million contract for AEHF satellites that will perform a 50% design adequacy assessment for the mission control segment and continue preparation for the preliminary design review as well as study the impacts on strategic command requirements. At this time, $4 million has been obligated (F04701-02-C-0002, P00383).

Satellites FY 2009

Beyond TSAT.

Sept 17/09: No TSAT. What Now? During a media roundtable with USAF Space Command’s Space and Missile Systems Center Commander, Lt. Gen. Tom Sheridan, he explains the way forward in the absence of TSAT. AEHF-4 and WGS F5/F6 have been added, but that will not make up the gap in space-based bandwidth. Meanwhile, the need for high bandwidth anywhere is exploding, thanks to the skyrocketing number of UAVs and other surveillance and/or remotely-operated platforms.

Efforts are now underway to look at the overall gap created by TSAT’s removal, determine the military’s overall priorities among military wideband (WGS), hardened (AEHF), or other bandwidth options, and figure out how that gap might be covered a piece at a time. New solutions will be an option, and so will the possibility of adding new technologies to existing platforms like AEHF.

If this doesn’t sound like a firm plan, it’s because there isn’t one yet. The current foci involve figuring out customer priorities, and finding near-term funding that would retain a number of TSAT personnel and engineers. Success in retaining these people is expected to ensure that they can bring their experience with next-generation technologies to help generate new options, and then analyze alternatives.

TSAT dead – long live AEHF!

Sept 14/09: Training. Lockheed Martin Corp. in Sunnyvale, CA received a $6.1 million contract to develop training material for increment 7, train the trainer for subject matter experts at Fort Gordon, and train international partners for the Advanced Extremely High Frequency Satellite program. At this time, $324,048 has been committed by the SMC/PKA in El Segundo, CA (F04701-02-C0002, P00353).

Sept 10/09: SV-4. Lockheed Martin Space Systems Company receives a $22 million contract for advance procurement of long-lead parts for AEHF Satellite Vehicle 4. At this time, $11 million has been committed (F04701-02-C-0002, P00379).

Sept 10/09: SV-1. Lockheed Martin announces that AEHF-1 has entered final testing at the company’s Sunnyvale, CA facilities, following successful completion of all spacecraft environmental testing. The Lockheed Martin-led team is now executing the final integrated spacecraft and system test procedures necessary to prepare the vehicle for flight. Over a 75-day period, the satellite will go through a series of factory tests to verify all spacecraft interfaces, demonstrate full functionality and evaluate satellite performance.

AEHF-1 was originally scheduled for launch in 2007, but the current release sets the bar for delivery at early 2010, and launch at an unspecified time in 2010. The 2nd and 3rd AEHF satellites are also progressing through final integration and test activities, and are currently on track for launch in 2011 and 2012 respectively.

March 31/09: GAO Report. American GAO auditors look at the AEHF program, as part of their 7th annual “Defense Acquisitions: Assessments of Selected Weapon Programs” report:

“For the second straight year, technical problems with satellite components resulted in a delay of the first launch. This latest delay is almost 2 years. Further, the program office estimates that the fourth AEHF satellite could cost more than twice the third satellite because some components that are no longer manufactured will have to be replaced and production will have to be restarted after a 4-year gap…

During system-level environmental testing of the first satellite, the program office identified six components with workmanship or design problems. Five of these components will need to be removed from the spacecraft for repair, and one will need a software fix. Once all components are repaired and reinstalled, the spacecraft will undergo environmental testing a second time to assure all components are working properly. Continued problems with integration and testing have led to additional schedule delays. The launch of the first satellite has slipped almost two years – from November 2008 to as late as September 2010. The launch of the second satellite was delayed from August 2009 to around June 2011, and the third satellite is now planned for launch in 2012. Due to these delays, initial operational capability has slipped 3 years – from 2010 to 2013.”

Feb 27/09: SV-4 lead-in. Lockheed Martin Space Systems in Sunnyvale, CA receives for $175 million for “the congressionally mandated advance procurement of long-lead parts in FY08 and FY09 for the Advanced Extremely High Frequency Satellite Vehicle four.” At this time $104.5 million has been committed (F04701-02-C-0002, POO347).

See also the $119.2 million July 18/06 contract. Each contract may not spend its full amount, but issued contracts to date now total $294.2 million.

Feb 27/09: Sub-contractors. Northrop Grumman delivers the payload module for AEHF-3. They are 22 days early, marking 3 consecutive early deliveries to the Lockheed Martin’s Sunnyvale, CA facilities (2007, 2008, 2009). Their payload module consists of the complete set of processing, routing and control hardware and software that handle the satellite’s communications, including critical features that protect against interception or jamming.

Lockheed Martin now will begin mating the payload module with its A2100 satellite bus and other space vehicle components, to be followed by environmental and acceptance testing of the completed satellite. NGC release.

Dec 30/08: TVAC issues. Lockheed Martin Space Systems in Sunnyvale, CA received a $7.2 million modifications, authorizing Lockheed to perform 2 additional thermal vacuum (TVAC) cycles on the AEHF Space Vehicles 2. As the Dec 16/08 entry notes, AEHF-1 is already facing problems due to TVAC related anomalies.

The US Air Force Space and Missile Systems Center (SMC), Military Satellite Communications Systems Wing at El Segundo, CA manages this contract (F04701-02-C-002, P00343).

Dec 30/08: Studies. Lockheed Martin Space Systems in Sunnyvale, CA received a $9.9 million modification to provide feasibility studies. These studies will center on extending the AEHF system in the Military Satellite Communications Program, which appears to bode ill for the $20+ billion TSAT program that was supposed to surpass AEHF. At this time, all funds have been obligated.

The US Air Force Space and Missile Systems Center (SMC), Military Satellite Communications Systems Wing at El Segundo, CA manages this contract (F04701-02-C-002, P00340).

Dec 16/08: TVAC issues. Lockheed Martin Space Systems Co. in Sunnyvale, CA receives a $252 million Change Order that will implement additional vehicle-level Thermal Vacuum (TVAC) testing for AEHF-1. The DefenseLINK release adds that:

“The first Advanced Extremely High Frequency (AEHF) satellite is undergoing a significant amount of rework on mission critical unit’s dues [sic] to anomalies.”

At this stage, anomalies are very bad news. Additional TVAC testing suggests that the problem affects the satellite’s ability to survive and operate in the vacuum and wildly varying temperatures that a space satellite must endure.

Testing fail forces contract

Nov 17/08: The latest Pentagon Selected Acquisitions Report finds the AEHF program on the announcements list again:

“Program costs increases $2,576.6 million from $5,645.3 million to $9,938.6 million (+35.0%) to reflect cost increases which have resulted in a critical Nunn-McCurdy unit cost breach currently undergoing certification review.”

This is slightly confusing, as the April 2008 announcement set costs at $7.36 billion – rising from $6.42 billion because they had added a 4th AEHF satellite to the program.

SAR – major cost breach

Satellites FY 2008

Cost increases. Antenna test
(click to view full)

Sept 16/08: Sub-contractors. Northrop Grumman Corporation announces that they have integrated all electronic units for AEHF-3’s payload module. The equipment includes approximately 20 electronics units that offer a complete set of radio frequency, processing, routing and control hardware, plus approximately 500,000 lines of software code.

NGC is currently under contract to provide 3 communications payloads to AEHF prime contractor Lockheed Martin in Sunnyvale, CA, and has delivered the first 2 on or ahead of schedule. This integration with Lockheed Martin’s A2100 satellite bus leaves the firm on track to maintain that record.

July 18/06: SV-4 lead-in. A $119.2 million modification to a cost plus award fee, cost-plus fixed-fee, cost-plus incentive-fee, firm-fixed-price contract with Lockheed Martin Space Systems Corp. of Sunnyvale, CA (F04701-02-C-0002, P00315). The modification covers long-lead parts for the 4th AEHF Satellite, and is an unfinalized contract whose exact numbers will be adjusted later. At this time $59.6 million has been committed.

April 7/08: Cost increases for the AEHF satellite and FAB-T terminal programs land them both on the Pentagon’s latest Selected Acquisition Reports release. The total increase is about 14.5% for the program as a whole, but the biggest increase is easy to understand – they added a satellite:

“[AEHF] Program costs increased $940.5 million (+14.6 percent) from $6,421.5 million to $7,362.0 million, due primarily to a quantity increase of one satellite from three to four satellites (+$946.0 million). Congress appropriated advance procurement for Space Vehicle 4 (SV-4) in the fiscal 2008 Appropriations Act. The Department added SV-4 Full Procurement in fiscal 2010, with a launch capability targeted in fiscal 2014.”

SAR – to 4 satellites

Feb 28/08: Testing. Lockheed Martin announces successful acoustic testing of the first Advanced Extremely High Frequency (AEHF) military communications satellite at its Space Systems facilities in Sunnyvale, CA. This test is designed to duplicate the sound and vibration levels expected during launch into orbit.

Lockheed Martin Space Systems and payload supplier Northrop Grumman Space Technology can now proceed with thermal vacuum testing, which tests performance in the enormously wide temperature extremes found in space. AEHF-1 will be shipped to the Air Force in late 2008 in preparation for launch aboard an Atlas V launch vehicle.

Satellites FY 2007

AEHF-1 meets EEVL. P&P integration
(click to view full)

June 18/07: Lockheed Martin announces that it has successfully integrated the AEHF’s spacecraft propulsion core structure and the payload module. The core structure contains the integrated propulsion system as well as panels and other components that serve as the structural foundation of the satellite. The payload module consists of spacecraft electronics as well as the complete set of payload processing, routing and control hardware and software that perform the satellite’s communications function.

The successful integration allows the team of Lockheed Martin Space Systems in Sunnyvale, CA and payload supplier Northrop Grumman Space Technology in Redondo Beach, CA to begin system level environmental and acceptance testing in preparation for launch in mid-2008. Lockheed Martin release.

June 1/07: Sub-contractors. Raytheon Co in Marlborough, MA received a $27.1 million3 firm-fixed-price contract for production, test, and delivery of 9 Extremely High Frequency (EHF) Satellite Communications Follow-On Terminal Communication Groups P/N: G752718-2 and 17 ship Antenna Groups P/N: G674898-1 (seven Radar Reducing Cross Section and ten Non-RRCS variants). This contract includes an option which, if exercised, would bring the cumulative value of this contract to $38.3 million.

Work will be performed in Largo, FL (61.8%); Marlborough, MA (36.8%); and Saint Pete, FL (1.4%), and is expected to be complete by May 2009. This contract was not competitively procured; it was synopsized as a sole source procurement via the Space and Naval Warfare Systems Command E-commerce web site on July 5, 2006. The Space and Naval Warfare Systems Command, San Diego, CA issued the contract (N00039-07-C-0001).

Feb 28/07: Lockheed Martin Corp. in Littleton, CO received a $108 million firm-fixed-price contract to launch AEHF-1 using an Atlas V Launch Vehicle under the Evolved Expendable Launch Vehicle (EELV) program. At this time, total funds have been obligated and work will be complete February 2009. The Headquarters Space and Missile Systems Center at Los Angeles Air Force Base, CA issued the contract (FA8816-06-C0004).

AEHF-1 launch contract

Dec 28/06: SV-1. Lockheed Martin Corp. Space Systems in Sunnyvale, CA received a $7.8 million cost-plus-award-fee contract modification for the use of a commercial payload processing facility to test, integrate, and fuel the Advanced Extremely High Frequency satellite in preparation for launch. This modification replaces the use of a government facility with a commercial facility that meets program requirements for floor space sufficient to support simultaneous mechanical and electrical launch processing operations. At this time, $1 million has been obligated. The Headquarters Military Satellite Communications Systems Wing at Los Angeles Air Force Base, CA issued the contract (F04701-02-C-0002/P00214).

Dec 22/06: SV-3. Lockheed Martin announces that it has delivered the flight structure for the 3rd AEHF satellite ahead of schedule. The flight structure, which is based on the A2100 geosynchronous spacecraft, will now be sent to Lockheed’s Mississippi facility for integration with its propulsion subsystem.

Over the next several months, a team of engineers and technicians at Lockheed Martin’s Mississippi Space & Technology Center, an advanced propulsion, thermal, and metrology facility located at the John C. Stennis Space Center, will integrate the spacecraft’s propulsion subsystem, which is essential for maneuvering the satellite during transfer orbit to its final location as well as conducting on-orbit operations and repositioning maneuvers throughout its mission life. See Lockheed Martin release.

Oct 19/06: Crypto. Lockheed Martin Space Systems Co. in Sunnyvale, CA received a $7.7 million cost-plus-award fee contract modification. This undefinitized contract action involves integration of the NSA-developed top secret key translation element into the AEHF system, and authorizes Lockheed Martin to start working the system design and test program changes required. The modification will develop, test and integrate the required hardware/software in to the AEHF mission control segment.

At this time, $4.5 million has been obligated. This work will be complete June 2019. The Headquarters Military Satellite Communications Systems Wing, Los Angeles Air Force Base, CA issued the contract (F04701-02-C-0002/P00212).

Oct 4/06: Changes. Lockheed Martin Space and Missiles in Sunnyvale, CA received a $7.6 million cost-plus-award fee contract modification for software and hardware changes to the Advanced Extremely High Frequency (AEHF) satellite system. The changes are necessary to develop and maintain backward compatibility with the predecessor Milstar communications satellite system, and are part of a series of modifications necessary to ensure this compatibility. The Headquarters Military Satellite Communications Systems Wing at Los Angeles Air Force Base, CA issued the contract (F04701-02-C-0002/A00013).

Satellites FY 2004 – 2006

Schedule slip. AEHF-1, 3. AEHF model test
(click to view full)

April 19/06: Testing. Lockheed martin engineers perform a successful modal survey for AEHF. It is designed to ensure that launch and other sources of vibrations such as reaction wheels, solar arrays and various deployable and steerable mechanisms will not affect the critical mission of the communications payload. The successful test was performed by a team of engineers at Lockheed Martin Space Systems, facilities in Sunnyvale, Calif. and included 292 accelerometers, 508 accelerometer channels and six shakers mounted to the structure and surrounding ground surface. Lockheed Martin release.

April 14/06: Lockheed Martin, Space Systems Co. in Sunnyvale, CA received a $454.9 million cost-plus fixed-fee, cost-plus award-fee contract modification for the implementation of the Advanced Extremely High Frequency (AEHF) Satellite Communication System Program re-plan, which started in late 2004.

The re-plan was necessary due to delayed delivery of government-furnished information assurance products, added payload component testing, and replacement of critical parts that were disqualified for space flight. The effort includes development of emulators, additional testing associated with integrating multiple incremental deliveries, and additional months of non-recurring development. The resulting AEHF first launch date of April 2008 is consistent with the revised Acquisition Program Baseline approved in March 2005. This work will be complete May 2010 (F04701-02-C-0002/P00136).

Major SDD increase

Jan 12/06: SV-3. Lockheed Martin Corp. Space Systems Co. in Sunnyvale, CA received a $491.2 million cost-plus-award-fee, cost-plus-fixed-fee, firm-fixed-price contract modification. This is a modification of the Advanced Extremely High Frequency (AEHF) satellite contract to add satellite vehicle #3 (SV3) as envisioned and permitted by a clause in the contract. This action includes the main SV3 contract, and introduces the option for Launch and Operations support.

The Launch and Operations Support option associated with this modification is planned to be exercised beginning in FY 2009 to support an FY 2010 launch, and the acquisition of SV3 will complete the AEHF program of record unless the T-SAT program is deferred or canceled (in which case AEHF SV4 & SV5 will be launched). Work on this contract, which takes the total amount of AEHF expenditures announced on DefenseLINK to $4.276 billion, is expected to be complete in May 2011 (F04701-02-C-0002, P00156).

AEHF-3 contracts

March 7/05: SV-3. Lockheed Martin Corp. in Sunnyvale, CA received a $78.2 million cost-plus award-fee, cost-plus fixed-fee, firm fixed-price contract modification to provide for the advance procurement of long-lead parts for AEHF Satellite Vehicles #3 (SV3) in FY05 (F04701-02-C-0002, P00102).

Dec 21/04: The U.S. Air Force announces that the AEHF program has suffered a 1-year schedule slip, and cost growth of about 20%. The first launch of the 3 planned satellites is now slated for April 2008 rather than 2007 [Source]. In its release, the USAF cites:

“…unavoidable delays and cost growth due to delayed delivery of information-assurance [signal-encryption] products, and the resulting delay of terminals required for satellite command and control… replacement of critical electronic parts and added payload component testing…”

Program slips

Aug 4/04: Spares. Lockheed Martin Corp. Space Systems in Sunnyvale, CA and Northrop Grumman Space Technology in Los Angeles, CA received a $32.55 million cost-plus award-fee contract modification for spare critical components to be used, if necessary, in factory by the contractor during assembly and test and of Advanced Extremely High Frequency (EHF) satellites.

Originally, 5 AEHF satellites were to be built, which ensured that there would be enough spare parts to avoid delays during production because the first satellites could use parts from satellites being assembled later. For this reason, the original AEHF plan did not include production spares. In November 2002, 2 of the Advanced EHF satellites were cancelled and the 3rd satellite was delayed one year, which meant there were no longer adequate numbers of spare critical parts to prevent production delays. Work will be complete by January 2009 (F04701-02-C-0002, P00083).

May 18/04: Crypto. Lockheed Martin Corp Space Systems and Northrop Grumman Space Technology received a $149 million contract modification which incorporates within-scope changes resulting from Revision to the KI-54 Cryptographic Interface Control Document (ICD).

The KI-54 ICD “black box” encryption device was modified by the NSA’s (National Security Agency) contractor, which meant the AEHF team was required to redesign the Host Accessory Logic Application Specific Integrated Circuit (HAL ASIC) in the AEHF communication payload. This effort was captured in Phase 1. In Phase 2, the AEHF contractor team will receive a 4 month program extension to identify and mitigate the risks and modifications to the whole satellite associated with this redesign. Locations of performance are: Lockheed Martin Corp. in Sunnyvale CA (51%) and Northrop Grumman in Los Angeles, CA (49%). This work will be complete in September 2008 (F04701-02-C-0002, P00061).

Dec 22/03: Changes. Lockheed Martin Missiles and Space in Santa Maria, CA received a $15 million cost-plus award-fee contract modification. This technical change will provide two different connection modes to allow MPE to communicate with Army and Air Force terminals and adapt to different terminal and network changes, as Option 5 of an analysis Study that defines Mission Planning Element (MPE) versus Terminal Functionality into the AEHF baseline. This work will be complete by September 2008 (F04701-02-C-0002, P00042).

Satellites FY 2002 – 2003

SDD contract; increase. older AEHF concept
(click to view full)

Aug 8/03: Crypto. Lockheed Martin Corp. in Sunnyvale, CA received a $78.5 million cost-plus award-fee, cost-plus fixed-fee, firm-fixed-price contract modification. It provides for an in-scope change to Incorporate KI-54 Interface Control Document (ICD) Revision F-Phase 2 impacts. The KI-54 ICD is a “black box” encryption device for military communications passing through AEHF. A two-phase approach was initiated to evaluate the KI-54 ICD Revision F changes. Phase I focused on the effort to redesign the HAL ASIC. Phase 2 focused on identifying and mitigating the AEHF system level impacts associated with the HAL ASIC redesign, as defined in Phase 1, such that the 4-month HAL ASIC PDR slip will not result in a launch delay. This work will be complete by September 2008 (F04701-02-C-0002, P00046).

July 23/03: Changes. Lockheed Martin Corp. Space Systems in Sunnyvale, CA and Northrop Grumman Space Technology in Los Angeles, CA received a $16 million contract modification for the following:

(1) Provide capability to assign any single uplink transmission security (TRANSEC) key to any beam;
(2) Provide capability to blank 2nd key contiguous bandwidth within any one permute group in multiples of wideband channels for every hope of the date frame. The blanking timing error shall be factory selectable and upload able from mission control segment (MCS);
(3) Allow extra high data rate users to acquire high gain earth coverage, reposition medium resolution coverage area (beam shared and full-time) and high-resolution coverage area beams without using super high gain earth coverage (SHGEC) uplink resources;
(4) Provide capability for all users to acquire and communicate in the same coverage requests, and the SHGEC which is only used for communications and time tracking terminals acquiring or communicating in any particular beam will do so using only one uplink TRANSEC key that is currently configured to that beam;
(5) Allow for permute group 0 group to support wideband channels.

This work will be complete in September 2008 (F04701-02-C-0002, P00043).

June 13/03: Changes. Lockheed Martin Corp. in Sunnyvale, CA received a $5.2 million contract modification to provide for in-scope changes to modify the Advanced Extremely High Frequency (AEHF) Payload. The technical change ensures backward compatibility with MILSTAR satellite operations. Specifically, it will provide users the capability to fence the necessary payload resources to process Rapid Reconfiguration Order Wire (RROW) streams, and the capability to control the fenced RROW XC2 stream processing payload resources as any other fenced resource, including sub-fences and sub-sub-fences, via command and access control protocol. The change will impact multiple specification documents including the Mission Planning Element of the Mission Control Segment, the Configurable Onboard Router in the Digital Processing Subsystem and the payload software. This work will be completed in September 2008 (F04701-02-C-0002, P00031).

Payload I&T
(click to view full)

May 27/03: Changes. Lockheed Martin Missiles and Space in Sunnyvale, CA received a $10 million cost-plus-award-fee, cost-plus-fixed-fee, firm-fixed contract modification. This is an in-scope change to redesign the host accessory logic circuit (ASIC) in response to a specification upgrade for the KI-54 cryptographic device. This effort will ensure secure communication capability by providing an improvement to the host accessory ASIC within the AEHF digital processing subsystem. This work will be complete January 2004 (F04701-02-C-0002, P00034).

May 22/03: SDD. Lockheed Martin Space Systems Co. received a $9 million contract modification as an amendment to the existing system development and demonstration (SD&D) contract that was definitized April 15, 2001. The purpose of this amendment is to increase the contract value from $2.63 billion to $2.64 billion. This increase is the result of an engineering change proposal to implement a new AEHF System alternate key management plan (AKMP). The effort is within scope of the existing contract, and is necessitated by requirement/design changes that meet National Security Agency (NSA) security requirements that have been validated by Air Force Space Command. The system keys can’t be produced until the NSA approves the AKMP, and these changes must be implemented to avoid possible impact to the launch schedule. The locations of performance are Lockheed Martin Missiles and Space in Sunnyvale, CA, and TRW Inc. Space and Electronics Group in Redondo Beach, CA. This work will be complete June 2008 (F04701-02-C-0002, P00029).

May 22/03: Lockheed Martin Corp. in Sunnyvale, CA is being awarded a $498 million firm-fixed-price contract modification. This is an amendment to the existing letter contract for the Advanced Extremely High Frequency (AEHF) System Development and Demonstration (SD&D) phase. The purpose of this amendment is to increase the not-to-exceed from $2.698 billion to $3.196 billion, as a result of the FY 2002 appropriation act decrease of $70 million and the loss of $30 million in international partner funding. Also, the not-to-exceed increase includes effort necessitated by the recent revision of the National Security Agency’s KI-54 encryption Interface control document, revision D in the amount of $46 million. This action provides for satellites replacement and upgrade of the associated ground command and control segment, and the necessary sustainment. The period of performance for this effort will span approximately 10 years.

Lockheed Martin Corp. will perform this effort at TRW Inc. Space and Electronics Group in Redondo Beach, Los Angeles, CA (46%), and Lockheed Martin Missiles and Space, Sunnyvale, CA (28%) and other locations (F04701-02-C-0002, P00007).

Major SDD increase

Nov 16/02: The Advanced Extremely High Frequency (AEHF) National Team, comprised of Lockheed Martin in Sunnyvale, CA, and TRW Inc. in Redondo Beach, CA, are being awarded a $2.698 billion (not-to-exceed) firm-fixed-price and cost-plus award fee contract for the System Development and Demonstration (SDD) phase of the AEHF satellite communication system program. This effort includes production of two satellites, plus replacement and upgrade of existing military satellite communication (MILSATCOM) ground command and control segment components to support AEHF and associated sustainment.

Solicitation for this sole source contract began in October 2000, negotiations were completed November 2001, and work will be complete in December 2011. The contractors will perform this effort in Sunnyvale, CA (45%), and Redondo, CA (55%). The Space and Missile Systems Center at Los Angeles Air Force Base, CA issued the contract (F04701-02-C-0002).

AEHF SDD contract: includes AEHF-1 & 2

FAB-T Terminals and Ground Control

FAB-T (Family of Advanced Beyond-line-of-sight Terminals) is designed to provide a family of software-defined radios that use a common open architecture to link to different satellites, and enable information exchange between ground, air and space platforms. It is envisioned as a common terminal for the next generation of High Data Satellite Communications using AEHF, Wideband Gapfiller, and other future satellite systems. Aircraft involved include bombers like the B-2 Spirit stealth bomber and B-52 Stratofortress, specialty platforms like the RC-135 Rivet Joint, E-4 NAOC, E-6 Mercury/TACAMO, et. al., and key UAV types like the RQ-4 Global Hawk and MQ-1/9 Predators.

The FAB-T family includes software-defined radios, antennas and associated user interface hardware that will provide a powerful system capable of hosting a multitude of transmission “waveforms” to accommodate data rates in excess of 300 megabits per second.

FAB-T Increment 1 will begin as a terminal for the AEHF and older Milstar satellite systems.

FAB-T Increment 2 will develop terminals to support Wideband Global SATCOM satellite operations on surveillance aircraft including key UAVs, with other platforms to follow.

Fortunately, FAB-T also is the first survivable Software Communications Architecture (SCA)-compliant communications system. Because its implementation will be software based, rather than hardware based, future upgrades that improve performance or extend the standard can be implemented without the time-consuming and expensive process of disassembling equipment and adding new electronics. These “future proofing” modifications can be made to any SCA-compliant radios if it is deemed necessary, even those outside the AEHF/FAB-T program.

Evolution Toward Competition E-6B Mercury
(click to view full)

While FAB-T was initially a Boeing program, Raytheon steadily won orders for AEHF-compatible terminals from every service, finally displacing Boeing in 2014.

FAB-T was initially a 6-year, $279 million system design and development contract in 2002, and it expanded to become an SDD/EMD and production program worth over $3.6 billion. Program activity was managed by Boeing’s Battle Management/Command, Control and Communications (BMC3) & Strategic Systems business segment in Anaheim, CA with key support from Boeing Satellite Systems of El Segundo, CA. Principal team members at the time included:

  • Boeing (Lead contractor, systems engineering and integration, system and terminal architecture, software development, test and evaluation, integrated logistics support and communications engineering)

  • Harris Corporation’s Government Communications Systems division in Melbourne, FL (integration of terminal and antenna hardware)

  • L-3 Communications’ Communications Systems West division in Salt Lake City, UT (development of the modem processor)

  • Northrop Grumman’s Mission Systems (not specified, but acquired TRW whose Command, Control and Intelligence Division in Fairfax, VA was working on AEHF waveform management)

  • Raytheon (related SMART-T terminals for USA, Canada and the Netherlands)

  • Rockwell Collins’ Government Systems Division (not specified)

  • ViaSat, Inc.’s Communications Systems Group in Carlsbad, CA (communications security module hardware and information security)

In September 2012, the USAF had run out of patience, and gave Raytheon a second crack at things with a limited FAB-T development contract. Raytheon had already managed to win a number of service-specific contracts for AEHF-compatible terminals from various branches of the US military (Army SMART-T, Navy MBT, STRATCOM MMPU) so their own development has been faster and less expensive than Boeing’s by a couple orders of magnitude.

Bu June 2014, Raytheon had become the USAF’s FAB-T CPT supplier as well, displacing Boeing and fielding the 1st set of FAB-T terminals onto command aircraft: the 4 national command post E-4Bs based on the 747, and the 16 E-6B Mercury Block IIs used as STRATCOM mirrors and “Looking Glass” theater command planes.

The USAF has deferred moves to equip its B-2A and B-52H bomber fleets, and its RC-135 Rivet Joint electronic eavesdropping jets. If they decide to go ahead, the contracts will be the subject of new competitions.

FAB-T & Ground Control: Contracts and Key Events FY 2012 – 2014

USAF gets annoyed, funds parallel design efforts; Raytheon wins FAB-T CPT competition, displacing Boeing.

E-4B mission
click for video

Aug 12/14: Raytheon VP and GM for Integrated Communication Systems Scott Whatmough says that they’ll be done FAB-T CPT testing by the end of 2014 (q.v. June 2/14). He adds that the B-2A Spirit stealth bomber would be a particularly challenging future addition, as its antennas are different from the B-52H or RC-135. Furthermore:

“It was a classified program when it was being developed and they came up with a very unique mechanical packaging concept for all of their electronics. Turns out no other aircraft ever adopted it, so it has a unique mechanical packaging.”

Sources: C4ISR & Networks, “Raytheon: FAB-T qualification testing done by year’s end”.

June 2/14: FAB-T contract. Raytheon in Marlborough, MA receives a $298 million firm-fixed-price and cost-plus-fixed-fee contract modification for 84 FAB-T Command Post Terminals (CPT), which will equip E-4B NAOC and E-6B Mercury Block II command post aircraft, as well as some ground and mobile locations. After FAB-T reaches Milestone C, Phase 2 production contract options for Low-Rate Initial Production and beyond will open up for Raytheon, expanding the contract considerably.

It’s a sharp blow to Boeing, but not entirely unexpected. On the other hand, it’s not the absolute end. Buying FAB-T terminals for USAF B-2 and B-52 bombers, RC-135 SIGINT/ELINT aircraft, or other planes, would require another procurement process.

Work will be performed in Marlborough, MA and Largo, FL, with the Florida location serving as the assembly point. USAF FY 2013 through 2019 budgets will fund FAB-T buys over time, with just $31,274 committed immediately. Two bids were solicited and two received. The USAF Life Cycle Management Center/HNSK at Hanscom AFB, MA, solicited 2 bids, and received 2 (FA8705-13-C-0005, PO 0002). Sources: Pentagon DefenseLINK | Raytheon, “Raytheon awarded $298 million for US Air Force FAB-T satellite terminal program” | Defense News, “Space Fence, FAB-T Awards Show an Emboldened DoD”.

Raytheon wins FAB-T CPT

Jan 28/14: DOT&E Testing Report. The Pentagon releases the FY 2013 Annual Report from its Office of the Director, Operational Test & Evaluation (DOT&E). The AEHF program is included, but the entry isn’t long and focuses on Mission Control Segment Increment 5 (MCS i5), which controls both Milstar and AEHF satellites.

The USAF hasn’t deployed the full AEHF MCS capability, so no conclusions can be drawn until testing is done in 2014. DOT&E did say that MCS i5 demonstrated improved reliability, dependability, and maintainability compared to i4, and was also more secure.

Jan 27/14: FAB-T situation. Raytheon VP of integrated communications systems Scott Whatmough has told reporters that the USAF is expected to award the FAB-T production contract by the end of March 2014. Raytheon is hoping to beat development contract holder Boeing, using its own privately-developed, AEHF-compatible receiver terminal.

The FAB-T program was most recently projected to cost $4.67 billion, a 48-percent increase from the original estimate of $3.17 billion, but the coming production order is expected to include just 84 FAB-T systems instead of the program’s 246. The bomber fleet installations have been put aside, and production systems will only be used in airborne and land-based command posts. Sources: DoD Buzz, “Pentagon May Award FAB-T Contract in March”.

Aug 1/13: Ground System. USAF Space Command accepts Mission Control Segment Increment 5 (MCS i5) for operational use as the Milstar and AEHF ground segment. It can support Low Data Rate and Medium Data Rate communications over a combined constellation of Milstar and AEHF satellites, and high-bandwidth Extended Data Rate (XDR) for command and control and some tactical communications. Sources: Pentagon DOT&E FY 2013 Annual Report.

July 1/13: FAB-T competition. Raytheon Network Centric Systems in Marlborough, MA receives a $34 million contract modification to continued development and testing of air (E-4B, E-6) and ground fixed and transportable command post terminals with presidential and national voice conferencing. The systems are a parallel project award under the Family of Advanced Beyond line-of-sight Terminals (FAB-T) program – q.v. June 19/13 and Sept 10/12 entries.

Work will be performed at Marlborough, MA, and is expected to be complete by October 2013. Fiscal 2012 Research and Development funds are being obligated at time of award. Air Force Life Cycle Management Center/HNSK, Hanscom Air Force Base, MA manages the contract (FA8307-12-C-0013, PO 0013).

June 19/13: FAB-T situation. Aviation Week reports progress on Raytheon’s competing FAB-T development contract (q.v. Sept 10/12).

Next month, Raytheon plans to complete work, including delivery of developmental terminal models for the E-4B and E-6B command post aircraft, and Presidential voice communications. The firm has just completed a critical design review (CDR), and an October 2013 test will involve satellite communications. The goal is a production-ready system by September 2014, and they’re basing their work on related AEHF-compatible wins like the US Army’s SMART-T (q.v. Oct 4/12), US Navy’s Multiband Terminal (MBT), and the USAF’s Minuteman Minimum Essential Emergency Communications Network Program Upgrade (MMPU, q.v. Dec 30/11).

Boeing hasn’t stopped working. Their CDR took place in 2012, and they’re now in the final stages of system level functional qualification. Demonstrations have taken place with AEHF and Milstar control systems, and flight tests are scheduled for this summer. Beyond FAB-T, one imagines that Boeing would like to win the upcoming Global Aircrew Strategic Network Terminal (GASNT) competition. Of course, so would Raytheon. Aviation Week.

Oct 4/12: SMART-T. Raytheon in Marlborough, MA receives a $164 million firm-fixed-price contract to create AEHF secure, mobile, anti-jam, reliable, tactical (SMART-T) terminals.

FAB-T isn’t the only game in town when it comes to AEHF-compatible terminals for sending and receiving data, and this is one of several service-specific contracts for AEHF-compatible terminals that don’t need all of FAB-T’s functionality, but may need other capabilities. See also Sept 19/11 entry.

Work location will be determined with each order, with an estimated completion date of Sept 28/15. The bid was solicited through the internet, with 1 bid received by U.S. Army Contracting Command in Fort Monmouth, NJ (W15P7T-12-D-0071).

Sept 10/12: FAB-T competition. About 10 years after losing the FAB-T contract, Raytheon Network Centric Systems in Marlborough, MA receives a $70 million firm fixed price contract for development, testing and production of FAB-T engineering development models of air (E-4B NAOC, E-6B TACAMO), ground fixed and transportable Command Post Terminals with Presidential and National Voice Conferencing (PNVC).

The location of the performance is Marlborough, MA. Work is to be complete by July 2013. The AFLCMC/HSNK at Hanscom AFB, MA manages the contract (FA8307-12-C-0013).

FAB-T becomes competitive

Dec 30/11: STRATCOM MMPU. Raytheon Network Centric Systems in Marlborough, MA receives a $9.4 million cost-plus-award-fee, firm-fixed-price, time-and-materials and cost reimbursement contract to upgrade the Minuteman Minimum Essential Emergency Communications Network Program to support AEHF constellation communications. The LM-30 Minuteman III ICBM is the land-based leg of the US nuclear weapons triad.

Work will be performed in Marlborough, MA, and is expected to be complete 12 months after receipt of order. The USAF ESC/HNSK at Hanscom AFB, MA manages the contract (FA8726-08-C-004, PO 0080).

FY 2010 – 2011

SAR shows program cost growth; Milstar ground control compatibility; Other firms producing AEHF-compatible terminals. Older Milstar II

Sept 19/11: SMART-T. Raytheon announces that they have fielded the first AEHF Secure Mobile Anti-jam Reliable Tactical Terminal (SMART-T) satellite communications solution to the U.S. armed services, using Raytheon’s eXtended Data Rate (XDR) waveform hardware and software modification.

SMART-T is compatible with EHF and AEHF satellites, and AEHF increases the data rate by a factor of 4x. Through 2015, Raytheon will field 364 AEHF SMART-T terminals to the U.S. armed services, 19 systems to Canada, and 7 to the Netherlands.

August 2011: Testing. Boeing successfully demonstrates high-data-rate transmissions between FAB-T and an AEHF test terminal, using the low probability of interception, low probability of detection extended data rate (XDR). XDR will be used for, among other things, nuclear command and control.

The testing covered XDR re-key, XDR text communications, dual FAB-T log-on with the AEHF payload, and interface with the AEHF Satellite Mission Control Subsystem. More than 50% of system integration tests are done, and system qualification testing is due to start in 2012. Note that Boeing’s Oct 3/11 release refers to Paul Geery as its FAB-T VP and program manager.

July 18/11: Testing. Boeing updates progress. The FAB-T EMD program has completed 90% of hardware qualification testing, 97% of all system software through-code and unit testing, and approximately 30% of systems integration and test. Boeing has conducted platform and payload integration testing through over-the-air low-data-rate tests and risk-reduction flight tests, and April 2011’s RC-135 Rivet Joint flight test of a Block 8 terminal was the 2nd in a series of airborne terminal tests, on the 1st operational program to be integrated.

Boeing is working toward the LRIP (low-rate initial production contract) for the Nuclear Command and Control Network Communications System, and completing qualification of the Block 8 third-generation hardware and high-data-rate waveform software. John Lunardi is currently Boeing’s FAB-T vice president and program director.

April 15/11: The Pentagon’s Selected Acquisitions Report ending Dec 30/10 includes the “significant cost changes” in AEHF program – both satellites and terminals. The FAB-T section reads:

“Program costs increased $630.9 million (+15.8 percent) from $3,981.9 million to $4,612.8 million, due primarily to complexities with software integration and challenges with hardware qualification (+$260.1 million), higher manufacturing costs due to loss of learning and production inefficiencies (+$258.9 million), and other increases due to the schedule stretch-out (+$134.7 million), partially offset by decreases in other support costs (-$32.7 million).”

SAR – cost increases

April 6/11: SDD. Boeing in Huntington Beach, CA receives a $271.2 million cost-plus-award-fee contract modification. It covers “the new estimated cost completion” amount for FAB-T’s System Development and Demonstration, and “provides increment funding aligned with Continuing Resolution authority.”

Work will be performed at Huntington Beach, CA, and Salt Lake City, UT. Hanscom AFB’s Electronic Systems Center, MA manages the contract (F19628-02-C-0048, PO 0219).

Major SDD Increase

Jan 26/11: Testing. A successful demonstration of over-the-air, low-data-rate communication between an orbiting Milstar satellite and the a 3rd generation (Block 8) FAB-T terminal, passing voice and data communication using the FAB-T’s low-data-rate software and its newly developed large aircraft antenna.

The system in question demonstrates why this kind of backward compatibility matters: it’s a Nuclear Command and Control Network Communications System. The team of Boeing, L-3 Communications, Rockwell Collins and ViaSat, Inc. will conduct more terminal integration, software testing and flight testing activities before building this system.

Boeing’s System Integration and Testing Lab in Huntington Beach, CA includes 12 FAB-T systems with connections to 3 antennas, allowing simultaneous over-the-air operation. 2011 will feature in-depth FAB-T system integration tests, now that over 80% of the hardware qualification testing and nearly 65% of the FAB-T software qualification testing is complete. The program is scheduled to enter flight testing in Q1 FY 2013 (fall 2012), and exercise its low rate initial production option in Q3 FY 2013 (summer 2013). USAF.

Oct 6/10: B-52s. Boeing in Wichita, KS received a $12.4 million contract modification for a future beyond line of sight (BLOS) communication capability on the B-52 heavy bomber, using AEHF-compatible BLOS terminals. At this time, $10 million has been committed by the ASC/WWVK at Wright Patterson AFB, OH (FA8107-05-C-0001; PO 0058).

This contract is part of the B-52 CONECT program.

Aug 3/10: AEHF & Milstar. Lockheed Martin announces that a joint company/USAF team has successfully transitioned the Milstar satellite constellation’s ground control system to the new AEHF Mission Control Segment (MCS). The AEHF MCS is now performing day-to-day operation of the USAs existing Milstar satellite constellation, leaving MCS ready to support deployment of AEHF-1 in August 2010. Lockheed Martin.

July 8/10: Integral Systems, Inc. in Columbia, MD receives a $13.4 million contract modification, extending the contract for the command and control system-consolidated (CSS-C) program for a year (from Sept 30/11 – Sept 30/12), due to launch delays on AEHF Space Vehicles 1, 2 and 3. At this time, no money has been committed; this contract just authorizes the funds if needed (F04701-01-C-0012, P00170).

CCS-C has been an overall money-saver for the USAF, migrating tracking, telemetry, and command and control from mainframe systems to cheaper and more flexible commercial client/server computing options. The USAF says that CCS-C sustainment costs are just 25% of the previous Satellite Control Network Command and Control Segment. After a competitive system ‘fly off’, in March 2002 Integral Systems Inc. (ISI) of Columbia, Maryland was awarded the CCS-C development/ sustainment contract. ISI/CCS-C employs approximately 130 people, and operates 2 software development laboratories in Maryland and Colorado.

Jan 4/10: FAB-T changes. Boeing in Huntington Beach, CA received a $34.3 million contract to implement the following changes to the functionality available for the Family of Advanced Beyond Line-of-Sight Terminals Increment 1: Contractor Technical Requirements Document (CTRD) update version 9.2; Simple Key Loader 6.0 interface to data set manager (DSM) for DSM flash control station profiles; and implementation of auto broadcast features on the Extended Data Rate (XDR) capability. At this time, $500,000 has been obligated. The 653 ESW/PK at Hanscom Air Force Base, MA manages the contract (F19628-02-C-0048-P00180).

Dec 1/09: Support. Lockheed Martin Space Systems in Sunnyvale, CA received a $39.5 million contract to provide sustainment for the AEHF satellite ground segment from Dec 1/09 – Sep 30/10 (F04701-02-C-0002, P00399).

Oct 21/09: Canada. Rockwell Collins announces a 5-year, USD$ 52.3 million contract to provide the Canadian Forces with AEHF-compatible Single Channel Anti-jam Manportable (SCAMP XDR-IPV, Extended Data Rate International Partners Variant) terminals. The Foreign Military Sale contract will be executed through the U.S. Army’s Communications-Electronics Command Group (CECOM).

Rockwell Collins’ SCAMP terminals provide worldwide secure, jam-resistant, covert, voice and data communications. They offer communication for a wide variety of applications and users. The terminals feature Extended Data Rate (EDR) capability that delivers data rates comparable to high quality, Digital Subscriber Line (DSL) modems.

SCAMP for Canada

Oct 14/09: Testing. Boeing Launch Services of Huntington Beach, CA received a $21.8 million contract modification to provide engineering development models for the Family of Advanced Beyond-Line-of-Sight Terminals (FAB-T) to allow for operational testing with production representative terminals. FAB-T terminals will connect soldiers or military platforms like planes, ships, et. al. with the AEHF constellation. At this time, $1.3 million has been obligated. The 653 ESW/PK at Hanscom Air Force Base in Massachusetts manages the contract (F19628-02-C-0048, P00171).

FY 2006 – 2009

FAB-T PDR, CDR.

June 26/09: AMACS antenna. Raytheon announces a successful test of their Advanced Multiband Communication Antenna System (AMCAS), developed for the U.S. Air Force. AMCAS is an extremely low-profile antenna that extends only 8 1/2″, and attaches to the aircraft’s metal skin rather than requiring complex in-fuselage installations. That configuration reduces drag, and minimizes time out of service during upgrades.

During the test, the AMCAS antenna communicated with the Milstar satellite’s medium data rate waveform, but it has been developed for use with FAB-T.

Oct 28-30/08: A successful system-wide Critical Design Review (CDR) for the FAB-T family. The Boeing Terminal Test team established log on, downlink, and uplink connections with a Milstar 6 satellite, as a first step toward implementing AEHF’s Extended Data Rate (XDR) waveform.

Formal qualification testing will now take place to validate the terminals’ interoperability and satellite interfaces, and Boeing expects to begin deliveries of engineering development modules to the Air Force in 2009 for FAB-T Increment 1. Flight testing of these modules is currently planned for mid-2009. Boeing release.

FAB-T CDR

Sept 16/08: Testing. Boeing announces that it has delivered its FAB-T Increment 2 prototype to the Massachusetts Institute of Technology’s Lincoln Laboratory in Lexington, MA, ahead of schedule. The lab will use it to continue developing the DVB-S2 based communications waveform.

Waveforms define how radios, satellites, et. al. communicate. The Lincoln Lab’s efforts will define a waveform used for airborne intelligence, surveillance and reconnaissance readout over Ka-band military satellite communications. That waveform can then be incorporated in air, ground, maritime, and space communications equipment as required, as long as they have the required hardware or are software-defined and SCA-compatible.

Sept 4/08: Changes. A $16.7 million cost plus award fee contract modification to Boeing of Anaheim, CA to update new platform requirements and Advanced EHF (AEHF) system interface. At this time, $7 million has been committed by the Air Force Materiel Command,’s Electronic Systems Center, 653d ELSG/PK at Hancom AFB, MA (F19628-02-C-0048, P00146).

July 28/08: Changes. A $53.4 million modification to Boeing in Anaheim, CA, in order to update new platform requirements and FAB-T’s AEHF system interface. The Electronic Systems Center of Air Force Materiel Command manages the contract (F19628-02-C-0048 P00143).

April 9/08: Changes. Boeing received a modified contract for $25 million to incorporate Engineering Change Proposal (ECP) 0035, Strategic Networks, into the Family of Advanced Beyond-Line-of-Sight Terminals (FAB-T) Increment 1 program. At this time $9.25 million has been obligated, and the contract amount will be finalized later. Hanscom AFB, MA issued the contract (F19628-02-C-0048/P00141).

April 7/08: Cost increases for the AEHF satellite and FAB-T terminal programs land them both on the Pentagon’s latest Selected Acquisition Reports release:

“[FAB-T] Program costs increased $454.8 million (+14.4 percent) from $3,167.4 million to $3,622.2 million, due primarily to a revised cost estimate resulting from analysis by the OSD Cost Analysis Improvement Group (+$348.8 million). Costs also increased due to a net quantity increase of 6 terminals from 216 to 222 terminals (+$44.7 million), adjustments in real and predicated escalation (+$26.6 million), an increase in initial spares (+$25.5 million), and a net stretch-out of the procurement buy profile (+$9.2 million).”

SAR – cost increases

Feb 15/08: Changes. Boeing of Anaheim, CA received a contract modification for $49.8 million. This undefinitized contract action to incorporate Engineering Change Proposal 0034, “New Platform Requirements and Advanced EHF System Interface Changes,” into the Family of Advanced Beyond-Line-of-Sight Terminals. At this time $17 million has been obligated. 653 ELSG/PKX at Hanscom Air Force Base, MA issued the contract (F19628-02-C-0048/P00138).

Feb 1/08: Testing. Northrop Grumman Corporation announces that it has demonstrated compatibility between the AEHF military communications satellite with user ground terminals using the new Extended Data Rate (XDR) waveform and protocols. Other future satellite communications programs, including the Transformational Satellite Communications System (TSAT) and the Enhanced Polar System, will also use XDR waveforms.

Earlier testing in May 2006 had already verified the backward compatibility of Advanced EHF with legacy terminals using Low Data Rate (LDR) and Medium Data Rate (MDR) waveforms. This latest demonstration included all 3, as 84 test objectives were demonstrated including links the U.S. Army’s Warfighter Information Network-Tactical terminal (WIN-T), the international variant of the Secure Mobile Anti-Jam Reliable Tactical Terminal (SMART-T), and Lincoln Laboratory’s Advanced Universal System Test Terminal (AUST-T).

Tests were conducted using a U.S. Army user terminal as well as a terminal configuration to be used by international partners, and included participants from the U.S. Air Force Space and Missile Systems Center, Northrop Grumman, the Joint Terminal Engineering Office, Lockheed Martin, the U.S. Army WIN-T program, the Lincoln Laboratory, and Raytheon (terminal manufacturer).

Jan 16/08: STRATCOM. Raytheon Network Centric Systems, Inc. of Marlborough, MA received a contract for $37.5 million. The firm will perform a Minuteman Minimum Essential Emergency Communications Network Program upgrade to support communications via AEHF satellite constellations. To give you an idea of just how serious that is, the Minuteman-III fleet is the USA’s set of land-based nuclear missiles. The upgrade will provide an improved terminal operator control function, add an AEHF and address other system improvement for the MMP. At this time $15.2 million has been obligated. The Electronic Systems Center, AFMC at Eglin Air Force Base, FL issued the contract (FA8726-08-C-0004).

Sept 14/07: Changes. Lockheed Martin Space Systems Corp. of Sunnyvale, Calif. received a contract modification for mission software improvements amounting to $16.9 million. Element 1 covers a change order to modify the Mission Planning Element of the AEHF’s ground software, which models the AEHF’s communication plan, to accurately model and support both current and new AEHF terminals. Element 2 of these modifications will allow the Mission Planning Element to distribute transmission security keys for terminals using the Ultra High Frequency (UFO/ MUOS) Follow-On Enhanced Extremely High Frequency (E/EE) or Interim Polar satellite systems. Finally, 2 increments of the Mission Planning Element software being developed in parallel will be combined to create efficiencies in software development and maintenance.

Taken together, these software improvements will also mitigate the risk of incompatible planning tools between the United States and its International Partners in future coalition operations. At this time $8,470,148 has been obligated.

Sept 4/07: Testing. Boeing announces the first time that its FAB-T system acquires an operational Milstar satellite and completes downlink data transmissions. The Low Data Rate test meets program schedule commitments and lays the foundation for uplink tests and other interoperability assessments later in 2007. The test, conducted from Rockwell Collins’ FAB-T Systems Integration Laboratory, used Boeing, RCI, ViaSat and L-3 Communications integrated hardware and software products. Boeing release.

June 26/07: Changes. Integral Systems, Inc. in Lanham, MD received a $5.8 million cost-plus-award-fee contract modification. It modifies the Command and Control System-Consolidated (CCS-C) effort to support the Wideband Gapfiller Satellite (WGS) Program Operations Readiness, add training, and incorporate changes to the system/Subsystem Specification (SSS) to clarify development requirements for the Advanced Extremely High Frequency (AEHF) satellite program.

The CCS-C program provides an upgraded capability to command and control the Air Force’s communication satellites, including the Defense Satellite Communication System, Milstar, Advanced Extremely High Frequency, and Wideband Gapfiller Satellites (N.B. now also called Wideband Global SATCOM, but this was the language of the US DefenseLINK release). At this time, $2 million has been obligated, and work will be complete in June 2010. The Headquarters Military Satellite Communications Systems Wing in Los Angeles Air Force Base, CA issued the contract (F04701-01-C-0012/P00118).

March 26/07: Recognition. Boeing announces that their joint replan of the FAB-T program in conjunction with U.S. Air Force Space Command has earned the USAF’s Agile Acquisition Transformation Leadership Award. Approximately 300 of the program’s 700-plus requirements were changed, along with detailed schedule re-phasing for development, test, delivery and installation. Boeing claims that the replan delivered new capability, while ensuring that “strategic nuclear command and control connectivity remains uncompromised.”

The award, presented in February 2007 to the Space Command’s FAB-T Alpha Contracting Team at the annual Acquisition Leaders Forum in Atlanta, Ga., recognizes the joint government-industry effort for completing a significant replan of the FAB-T program in a record 10 weeks during the summer of 2006. The award also acknowledges skill in acquisition program management and leadership bringing about acquisition process transformation. Boeing release.

Feb 13-17/07: CDR. Team Boeing successfully completes a an external Critical Design Review (CDR) for FAB-T, paving the way for deliveries to begin. The CDR follows the recent delivery of a Block 4 software-defined radio to the U.S. Air Force, and successful Preliminary Design and Integrated Baseline reviews. Initial FAB-T deliveries will begin in December 2008.

A CDR needs to demonstrate that the program’s requirements are defined and understood to a point that gives the review board confidence in the team’s ability successfully execute a production contract. In this case key requirements included a survivable command and control capability for the next generation AEHF satellite constellation, plus demonstrated compatibility with the Extremely High Frequency Low Data Rate (EHF LDR) waveform, which forms the basis for future Advanced EHF (AEHF) waveforms and block upgrades. SCA-compliant EHF LDR compatibility also provides a base for hosting new waveforms being developed for the T-SAT (Transformational Satellite Communications) program. Boeing release.

Dec 11/06: Sub-contractors. ViaSat, Inc. finalizes a $35 million dollar subcontract modification with Boeing Integrated Defense Systems. This award adds additional technical requirements to the ViaSat FAB-T subcontract, and extends ViaSat product development and support through 2011. See ViaSat press release. To date, ViaSat has completed two major FAB-T program deliveries. Acceptance testing on the Prototype phase is complete and has been delivered to the U.S. Air Force as part of the Boeing team FAB-T terminal delivery. Boeing has also taken delivery of the FAB-T engineering development model hardware and software.

Nov 28/06: Mission planning. Lockheed Martin Space Systems Co. in Sunnyvale, CA received a $51 million cost-plus-award fee contract modification. This modification of the Advanced Extremely High Frequency (AEHF) MILSATCOM Systems Wing contract provides for transition from legacy Milstar ground control and mission planning equipment to new AEHF equipment. This realignment is necessary to account for delays in the delivery of new command post terminals, and the need to reduce the operational impact of the transition. This realignment also includes a program decision to upload the final planned increment of satellite software capability before launch rather than afterward, to avoid an interruption to future operations. The effect of these decisions is to extend the turnover date by 7 months for additional preparation and tests, though the launch date remains unchanged. At this time, $8 million have been obligated. Work will be complete May 2010.

Oct 17/06: Boeing has successfully completed a Preliminary Design Review for the FAB-T program, a key milestone. Attended in Anaheim, CA by more than 150 Boeing, senior government and industry officials, the four-day review included presentations from systems, software and hardware teams. Part of the key criteria were that Boeing and its industry team had to show that they had successfully incorporated schedule and requirement changes that are part of the program’s new baseline. See release.

FAB-T PDR

Sept 27/06: Changes. Boeing Co. C3 Networks in Anaheim, CA received a $465.9 million cost-plus award fee contract modification. This modification will incorporate Engineering Change Proposal 0020 replan into the Family of Advanced Beyond-Line of Sight Terminals (FAB-T) increment 1 program. FAB-T terminals will connect soldiers or military platforms like planes, ships, et. al. with the AEHF constellation. The ECP 0020 replan addresses changes necessary to implement an executable program within cost and schedule objectives that will support AEHF requirements.

Specifically, the replan addresses the following: program overruns; requirements deferrals and accelerations; requirements deletions; pending requirements changes that will enable FAB-T to meet external requirements from concurrently evolving systems e.g., the AEHF payloads; and the INFOSEC module for FAB-1. The replan also includes the option to support government interoperability testing. Work will be complete December 2011. The Headquarters 653d Electronic Systems Wing at Hanscom Air Force Base, MA issued the contract (F19628-02-C-0048/P00095).

NB. The DefenseLINK release adds that “at this time, $1,761,770 have been obligated,” – which makes little sense as it is 4 times larger than the contract award. We’ve asked PA POC Monica Morales at (781) 377-8543 to clarify.

FY 2002 – 2005

SDD contract.

March 10/05: Crypto issues. The NSA (National Security Agency) issued modified handling instructions during development, integration and testing of the FAB-T modem processor group, because of delays in their Cryptographics Verification and Design Verification testing of the ACTS cryptographic devices. In order to comply with the modified ACTS handling guidance, Boeing in Anaheim, CA received a $10.5 million cost-plus award-fee Undefinitized Contract Action (UCA) for Contract Change Proposal (CCP)-0011: ACTS (Security Chip) Handling procedures. This guidance requires physical security and emanation protection of the test facility, and will limit contact with the test equipment to personnel with appropriate clearances. The Headquarters Electronic Systems Center at Hanscom Air Force Base, MA issued the contract (F19628-02-C-0048, P00051), which is expected to end in September 2008.

Dec 21/04: Program slips. The U.S. Air Force announces that the AEHF program has suffered a 1-year schedule slip, and cost growth of about 20%. The first launch of the 3 planned satellites is now slated for April 2008 rather than 2007 [Source]. In its release, the USAF cites:

“…unavoidable delays and cost growth due to delayed delivery of information-assurance [signal-encryption] products, and the resulting delay of terminals required for satellite command and control… replacement of critical electronic parts and added payload component testing…”

Program slips

Dec 8/04: Changes. The Boeing Co. in Anaheim, CA receives a $42.5 million cost-plus award-fee contract modification for Family of Advanced Beyond Line-of-Sight Terminals (FAB-T), ECP 0011: Incorporated of additional Advanced Extremely High Frequency (AEHF) COMSEC/TRANSEC System (ACTS) chip and keying material delays into the FAB-T baseline; and update of FAB-T and AEHF baseline specifications. This contract modification incorporates both the most recent ACTS-related delays and synchronization with the maturing AEHF specifications. These modifications will be incorporated into 16 AEHF Engineering Development Models of terminals for the B-2, B-52, E-4, E-6, and RC-135 aircraft and for ground-fixed and ground-transportable command post terminals. At this time, $10 million has been obligated and work will be complete by September 2008. The Headquarters Electronic Systems Center at Hanscom Air Force Base, MA issued the contract (F19628-02-C-0048, P00040). The DefenseLINK release adds that:

“ACTS chip and ACTS keying material delays have occurred since FAB-T contract F19628-02-C-0048 award, driving schedule delays in both the AEHF and FAB-T schedules. In addition, AEHF system-level and inter-segment specifications have matured through working groups involving the government, Boeing, and the AEHF system contractor team.”

Aug 24/04: Changes. Boeing Co. in Anaheim, CA receives a $20.2 million cost-plus award-fee contract modification to bring FAB-T into line with changes in the AEHF specification. At this time, $2.1 million of the funds have been obligated, and work will be complete by December 2007. The Headquarters Electronic Systems Center at Hanscom Air Force Base, MA issued the contract (F19628-02-C-0048, P00028). The DefenseLINK release openly acknowledges that:

“At the time the FAB-T contract F19628-02-C-0048 was signed, the Advanced Extremely High Frequency (AEHF) specifications referenced in the contract were not complete and/or mature. Since that time, the (AEHF) system design and specifications have been maturing through working groups involving the Government, Boeing and the AEHF system Contract Team…”

Aug 04/04: PDR. The Boeing team announces completion of “a highly successful Preliminary Design Review (PDR) in Anaheim,” which included both systems-level and software reviews. See release.

Sept 24/02: The U.S. Air Force’s Electronic Systems Center (ESC) at Hanscom Air Force Base, MA announced Boeing as the prime contractor for a 6-year, $273 million contract to design and develop the first increment of FAB-T. See release.

SDD contract

April 29/02: The Boeing Space and Communications Family of Advanced Beyond Line-of-Sight Terminals (FAB-T) team announces the delivery of their proposal. Boeing Space and Communications (S&C) is leading one of two industry teams competing for a 6-year, $279 million system design and development contract, which will be managed by the MILSATCOM Terminals Office at Electronic Systems Center, Hanscom Air Force Base, MA.

The proposal submitted by the Boeing team represents the first increment of the multi-phase program, where the winning team will have sole responsibility for a 6-year period of performance upon award in late June 2002. At the time of release, the initial design period is expected to be followed by the low-rate initial production phase in 2007, and the production phase in 2008. The system is expected to be fully operational by 2009. See release.

Additional Readings & Sources

 

Related Ground Systems

 

News & Views

Categories: Defence`s Feeds

Spanish and US defence industry assocations look to collaboration

Jane's Defense News - Fri, 22/05/2015 - 02:00
Spanish and US defence industry associations TEDAE and NDIA have signed a collaboration accord aimed at increasing co-operation and interchange of information between the two. The agreement followed a joint workshop meeting in Washington that was attended by 15 Spanish companies and 70 of their US
Categories: Defence`s Feeds

Spanish and US defence industry associations look to collaboration

Jane's Defense News - Fri, 22/05/2015 - 02:00
Spanish and US defence industry associations TEDAE and NDIA have signed a collaboration accord aimed at increasing co-operation and interchange of information between the two. The agreement followed a joint workshop meeting in Washington that was attended by 15 Spanish companies and 70 of their US
Categories: Defence`s Feeds

Taiwan 'welcomes' congressional pressure over RIMPAC invitation

Jane's Defense News - Fri, 22/05/2015 - 02:00
Taiwan's Ministry of National Defense (MND) says it "welcomes" moves by the US House of Representatives to add an amendment to the fiscal year 2016 US defence budget that includes a clause urging Taiwan's participation in the biennial Rim of the Pacific (RIMPAC) exercise. The House passed
Categories: Defence`s Feeds

'No technical problem' in crashed Hungarian Gripen

Jane's Defense News - Fri, 22/05/2015 - 02:00
Technical faults were not behind the crash of a Hungarian Air Force Saab Gripen fighter aircraft on 19 May, Czech Defence Minister Martin Stropnicky said. "It was reported that there was no technical problem," Stropnicky said as he visited Caslav Air Base in the Czech Republic where the
Categories: Defence`s Feeds

A400M operators warned to check engine control units following crash

Jane's Defense News - Fri, 22/05/2015 - 02:00
Airbus has recommended that operators of the A400M Atlas transport aircraft perform checks on the aircraft's engines "to avoid potential risks in any future flights". The announcement comes in the wake of the fatal crash of MSN23 on 9 May. In a statement, Airbus said on 19 May it had
Categories: Defence`s Feeds

ANDSF claims success in Ghazni, breaks Taliban siege in Ghor

Jane's Defense News - Fri, 22/05/2015 - 02:00
The Afghan National Defense and Security Forces (ANDSF) reported in early May they had conquered the district of Nawa in the southeastern province of Ghazni, which had been under Taliban control for the last nine to ten years. However, Mohammad Aref Rahmani, a member of parliament from Ghazni, told
Categories: Defence`s Feeds

BAE Systems to invest in Clyde facilities, opts to retain two sites

Jane's Defense News - Fri, 22/05/2015 - 02:00
Key Points BAE Systems abandons plans to concentrate all shipbuilding activity in a new facility at Scotstoun Two site plan calls for over GBP100 million investment at Govan and Scotstoun sites BAE Systems Naval Ships has pulled back from plans to consolidate its Glasgow shipbuilding activities
Categories: Defence`s Feeds

Bangladesh PM calls for defence industry development

Jane's Defense News - Fri, 22/05/2015 - 02:00
Bangladesh Prime Minister Sheikh Hasina has outlined a target for local defence companies to enhance capability in order to reduce dependency on imports. In comments published on 21 May by the government-run National News Agency of Bangladesh (BSS), Hasina called on local defence enterprises -
Categories: Defence`s Feeds

Belgian NH90s reach initial operational capability

Jane's Defense News - Fri, 22/05/2015 - 02:00
Belgium's NHIndustries NH90 multirole helicopters have declared their initial operating capability, it was announced on 20 May. The chief of the Belgian Air Component, Major General Frederik Vansina, said the 18th Squadron in Beauvechain was now ready for operations in a non-hostile environment.
Categories: Defence`s Feeds

Bulgaria to launch fighter programme

Jane's Defense News - Fri, 22/05/2015 - 02:00
Bulgarian defence minister Nikolai Nenchev has revealed that the country is to launch a fighter procurement by the end of June. According to Bulgarian media reports on 21 May, Nenchev told a parliamentary defence committee that the procurement would replace a number of aircraft. However, it was
Categories: Defence`s Feeds

Colombia's defence minister and ambassador to the US swap jobs

Jane's Defense News - Fri, 22/05/2015 - 02:00
Juan Carlos Pinzón stepped down from his position as Colombia's defence minister on 19 May and will take on a new role as Colombia's ambassador to the United States. During Pinzón's tenure the armed forces grew by 18 mobile brigades, two marine brigades, and nine task forces. They also
Categories: Defence`s Feeds

Exelis, Harris merger given green light by shareholders

Jane's Defense News - Fri, 22/05/2015 - 02:00
Exelis and Harris have been given the support of their shareholders to merge, Exelis announced on 22 May. The US Department of Justice has also approved the merger, which had generated anti-trust concerns over a potential market concentration. The two companies now expect the merger, valued at
Categories: Defence`s Feeds

French defence spending increase boon for procurement

Jane's Defense News - Fri, 22/05/2015 - 02:00
Key Points France is to spend an extra EUR1.5 billion on defence equipment by 2019 under an update to the country's military programming law Included is the addition of four C-130s, more helicopters, and the acceleration of several naval programmes French defence minister Jean-Yves Le Drian
Categories: Defence`s Feeds

IMDEX 2015: CMN introduces MCM variant of Ocean Eagle trimaran

Jane's Defense News - Fri, 22/05/2015 - 02:00
Key Points CMN has unveiled a mine countermeasures variant of the Ocean Eagle 43 patrol boat The vessel is positioned to meet the demands of modern mine warfare operations, company says French shipyard Constructions Mécaniques de Normandie (CMN) has introduced a mine countermeasures (MCM)
Categories: Defence`s Feeds

IMDEX 2015: ST Marine, KBR in joint talks for Australia's Pacific Patrol Boat Program

Jane's Defense News - Fri, 22/05/2015 - 02:00
Singapore shipbuilder ST Marine is in talks with Texas-based engineering company Kellogg Brown & Root (KBR) to jointly bid for Australia's Pacific Patrol Boat Replacement Program, a source has confirmed to IHS Jane's during the IMDEX 2015 exhibition in Singapore. The potential collaboration
Categories: Defence`s Feeds

Indian Coast Guard commissions four more patrol vessels

Jane's Defense News - Fri, 22/05/2015 - 02:00
The Indian Coast Guard has commissioned four new vessels at Porbandar in the western state of Gujarat. The vessels - the Aadesh-class fast patrol ship ICGS Ankit (pennant number 247) and the interceptor boats C-419, C-420, and C-155 - were commissioned on 14 May. In recent months, the coastguard
Categories: Defence`s Feeds

Iraqi Kurdistan president likely to cite constitutional uncertainty and security perils to extend presidential term

Jane's Defense News - Fri, 22/05/2015 - 02:00
Key Points The Kurdistan Region's constitution is unlikely to be amended before President Massoud Barzani's term expires, increasing the likelihood that elections will be postponed and his term extended by at least a year. The Patriotic Union of Kurdistan (PUK) and the Gorran party - which
Categories: Defence`s Feeds

Italy cracks down on environmental crime

Jane's Defense News - Fri, 22/05/2015 - 02:00
Key Points Environmental crimes are lucrative ventures for organised crime groups in Italy, particularly in Campania and Lombardy. The state response is hindered by corruption in local administrations, although a new law has been passed that elevates environmental crimes to the status of felony.
Categories: Defence`s Feeds

JTIC Brief: Striking back - fall of Ramadi highlights largely undiminished Islamic State threat

Jane's Defense News - Fri, 22/05/2015 - 02:00
Key Points The Islamic State took control of the city of Ramadi, capital of Iraq's Anbar province, on 17 May, following heavy fighting with security forces. The city was the first major Iraqi urban centre to be seized since security forces and militias recaptured Tikrit in late March, representing
Categories: Defence`s Feeds

Pages