You are here

Defence`s Feeds

Virginia Block III: The Revised Bow

Defense Industry Daily - Thu, 11/04/2019 - 05:58

Virginia Block I-II
(click for SuperSize)

GDEB Receives $148M as Virginia Class Lead Yard” described changes to the Virginia Class submarine’s design that are expected to reach 20% of the $200 million savings goal by the time orders for the versatile sea attack/ land attack/ special forces submarines rise to 2 per year, in 2012.

The bow changes cover the FY 2009-2013 ships, referred to as Block III. SSN 774 Virginia – SSN 777 North Carolina are Block I, and SSNs 778-783 will be Block II. Block III begins with the 11th ship of class, SSN 784. Long lead time component orders began May 22/08, and the submarine is expected to be ready for delivery around 2015. A fuller explanation of Block III’s extensive bow changes, and an accompanying graphic, may be found below – along with contract updates that include additional improvements and sonar development.

The Virginia Class Program: “2 for 4 in 12”

SSN 777 costruction
(click to view full)

The SSN-774 Virginia Class submarine was introduced in the 1990s as a Clinton-era reform that was intended to take some of the SSN-21 Seawolf Class’ key design and technology advances, and place them in a smaller, less heavily-armed, and less expensive platform. The resulting submarine would have learned some of the Seawolf program’s negative procurement lessons, while performing capably in land attack, naval attack, special forces, and shallow water roles. In the end, the Seawolf Class became a technology demonstrator program that was canceled at 3 ships, and the Virginia Class became the naval successor to America’s famed SSN-688 Los Angeles Class.

The Virginia Class program was supposed to reach 2 submarines per year by 2002, removing it from the unusual joint construction approach between General Dynamics Electric Boat and Northrop Grumman Shipbuilding – but that goal has been pushed back to 2012 in progressive planning budgets.

In FY 2005 dollars, SSN-21 submarines cost between $3.1-3.5 billion each. According to Congressional Research Service report #RL32418, and the Navy is working toward a goal of shaving FY05$ 400 million from the cost of each Virginia Class boat, and buying 2 boats in FY2012 for combined cost of $4.0 billion in FY 2005 dollars – a goal referred to as “2 for 4 in 12”. In real dollars subject to inflation, that means about $2.6 billion per sub in 2012, and $2.7 billion in 2013. The Navy believes that moving from the current joint construction arrangement will shave FY05$ 200 million from the cost of each submarine, leaving another FY05$ 200 million (about $220 million) to be saved through ship design and related changes.

Block III: The Changes

Block III bow mods
(click to view full)

The most obvious change is the switch from 12 vertical launch tubes, to 12 missiles in 2 tubes that use technology from the Ohio Class special forces/ strike SSGN program. The Virginia’s hull has a smaller cross-section than the converted ballistic missile SSGNs, so the “6-shooters” will be shorter and a bit wider. Nevertheless, they will share a great deal of common technology, allowing innovations on either platform to be incorporated into the other submarine class during major maintenance milestones. Net savings are about $8 million to program baseline costs.

The other big change you can see in the above diagram is switching from an air-backed sonar sphere to a water-backed Large Aperture Bow (LAB) array. Eliminating the hundreds of SUBSAFE penetrations that help maintain required pressure in the air-backed sonar sphere will save approximately $11 million per hull, and begins with the FY 2012 boats (SSNs 787-788).

The LAB Array has 2 primary components: the passive array, which will provide improved performance, and a medium-frequency active array. It utilizes transducers from the SSN-21 Seawolf Class that are that are designed to last the life of the hull. This is rather par for the course, as the Virginia Class’ was created in the 1990s to incorporate key elements of the $4 billion Seawolf Class submarine technologies into a cheaper boat.

The SUBSAFE eliminations, plus the life-of-the-hull transducers, will help to reduce the submarines’ life cycle costs as well by removing moving parts that require maintenance, eliminating possible points of failure and repair, and removing the need for transducer replacements in drydock.

The bow redesign is not limited to these changes, however, and includes 25 associated redesign efforts. These are estimated to reduce construction costs by another $20 million per hull beginning with the FY 2012 submarine.

With the $19 million ($11 + 8) from the LAB array and Vertical Payload, and the $20 million from the associated changes, General Dynamics is $39 million toward the $200 million baseline costs goal of “2 for 4 in 12”. While the changes themselves will begin with the FY 2009 ship, the savings are targeted at FY 2012 because of the learning curve required as part of the switch. Recent discussions concerning an earlier shift to 2 submarines per year would result in faster production of the Block III submarines, but would be unlikely to make a huge difference to that learning curve.

Contracts and Key Events

Tomahawk launched

April 11/19: ETCU The Navy awarded $33.4 million to Raytheon to supply the Naval Warfare Center in Philadelphia with up to 28 electronic throttle control units (ETCU) and auxiliary components in support of the Virginia Class program. The deal has Raytheon provide replacement ETCU hardware, which is currently obsolete and can no longer be efficiently supported. The Virginia Class are attack submarines. The Navy’s newest undersea warfare platform is designed to seek and destroy enemy subs as well as surface ships. Virginia Class boats can carry up to 24 torpedoes and Tomahawk cruise missiles. They can be deployed for a wide range of operations including anti-submarine warfare, anti-surface ship warfare, strike warfare, special operations forces support, intelligence, surveillance and reconnaissance, irregular warfare, and mine warfare missions. According to the DoD, the proposed contract includes the hardware fabrication for new construction platforms and all back-fit systems to mitigate parts obsolescence, update and maintain the ETCU technical data package, and design verification testing on limited production units for quality assurance. Work is scheduled to be completed by April 2024.

March 20/19: Long Lead Time Material The US Navy awarded General Dynamics a $2 billion contract modification to provide additional materials required to build the Virginia Class submarines from fiscal 2019 through fiscal 2023. The deal includes additional Long Lead Time Material and Economic Ordering Quantity items for SSN-802 to SSN-811 underwater vessels. The SSNs 802 -811 Virginia Class submarine hull numbers have not been named yet. The Virginia Class is the Navy’s newest undersea warfare platform. Attack submarines are designed to seek and destroy enemy submarines and surface ships, project power ashore with Tomahawk cruise missiles and Special Operation Forces, carry out Intelligence, Surveillance, and Reconnaissance (ISR) missions, support battle group operations, and engage in mine warfare. The modification falls under a previously awarded sole-source contract. General Dynamics is the lead contractor of the Virginia Class submarine program. In February 2017, General Dynamics won an initial $126.5 million contract by the US Navy for long lead time material for the first two Block V Virginia Class submarines, SSN-802 and SSN-803. The Block V submarines built from 2019 onward will have an additional Virginia Payload Module (VPM) mid-body section, increasing their overall length. Work under the contract modification will take place within the USA.

February 27/19: Universal Modular Mast The US Navy awarded L-3 KEO a $19.3 million contract modification for the production of the Universal Modular Mast, which serves as a lifting mechanism for the Virginia class mast payloads. The Universal Modular Mast is standard equipment for above-water sensors on U.S. and international submarines. It is a non-hull penetrating mast for Navy Virginia-class fast-attack submarines and Ohio-class guided missile submarines that can host five different sensor configurations: the photonics mast, the multi-function mast, the integrated electronic mast, the high-data-rate-mast, and the photonics mast variant. The Virginia class or SSN-774 class are nuclear powered fast attack submarines. The submarines form the Navy’s new undersea warfare platform designed to seek and destroy enemy submarines and surface ships as well as project power ashore. Work under the contract will take place in Italy as well as Massachusetts and is scheduled to be finished by August 2021.

April 02/18: Post-delivery work General Dynamics Electric Boat Corp, is being contracted for the provision of post-delivery work on the USS Colorado (SSN 788). The awarded contract is valued at over $14 million. The USS Colorado is the 15th Virginia Class submarine delivered to the US Navy. She was delivered on September 21, 2017 and was commissioned on March 17, 2018. The SSN 788 is part of a 5-year, $17 billion deal to strengthen the USA’s nuclear submarine fleet. The SSN 788 belongs to Block III submarines that took a big step forward by replacing the 12 vertical launch tubes with a more flexible “6-shooter” approach, and swapping a water-backed, horseshoe-shaped LAB sonar array for the existing air-backed spherical array. Electric Boat Corp. will perform planning and execution efforts, including long lead time material procurement, in preparation to accomplish the maintenance, repair, alterations, testing, and other work on USS Colorado. Work will be performed in Groton, Connecticut and is expected to be completed by September 2018.

Jan 5/09: Goodrich in Charlotte, NC received a $49 million contract from Northrop Grumman Shipbuilding to provide composite components for the next 8 Virginia Class nuclear fast attack submarines referred to as Block III.

Goodrich’s Engineered Polymer Products team in Jacksonville, FL is building components to support the construction of 1 ship per year in 2009 and 2010, rising to 2 ships per year from 2011 through 2013. The components include the bow dome, and sonar and weapons equipment.

Dec 22/08: The US Navy signals its a href=”/Early-Xmas-Big-Virginia-Contracts-for-GDEB-NGC-05218/”>approval of the Virginia Class’ progress, and of the new Block III design, with a $14.011 billion contract to fund 8 Virginia Class block III submarines. Work on these boats will run until 2019.

Dec 12/08: General Dynamics Electric Boat Corp. in Groton, CT received a $16.8 million cost-plus-fixed-fee material order to fund the Block III Common Weapon Launcher (CWL) design, and includes the total scope associated with the vendor portion of the inboard electronics design as well as the scope required for in-house (Electric Boat) tasks. The CWL will sit in the Block III bow’s “six shooter” holes, and is so named because that space can be used to launch a wide variety of items besides UGM-109 Tomahawk cruise missiles; aerial UAVs and underwater UUVs are the most obvious.

GDEB services will include engineering support, Engineering Development Model (EDM) hardware, continued development of the CWL for use with SSN 784 VPT, development of interface documents, and defining changes to support interfaces to the Weapon Control and Payload Tube Control Panels. Work will be performed in Manassas, VA, and is expected to be complete by 2013. This contract was not competitively procured by the supervisor of Shipbuilding Conversion and Repair in Groton CT (N00024-09-C-2101).

Dec 12/08: Lockheed Martin Maritime Systems and Sensors in Manassas, VA received a $38.3 million modification to previously awarded contract (N00024-04-C-6207) for engineering services in support of the Acoustic – Rapid Commercial off The Shelf (A-RCI) program. The 550,000 additional engineering services hours will be used on TacLAN tasking related to Special Operations support, and to complete the new “BSY-2 Wrap Around Antenna (WAA),” which is listed as being a Virginia Class sonar.

DID requested clarification, and got it. BSY-2 is a Seawolf class system only. WAA is the Wide Aperture Array, and on the SSN-774 Virginia Class it evolved to the L-WAA (Lightweight Wide Aperture Array). The Virginia Class Block III bow has been redesigned to save money beginning with SSN 784; it will use the Large Aperture Bow (LAB) Array.

It turns out that the DefenseLINK release should read “technology insertions for the USS Jimmy Carter’s [SSN 23 Seawolf Class] BSY-2 WAA, and USS North Carolina [SSN 777 Virginia Class] LWAA TI-08 integration.” The exact work involved is technology insertion, integration, and modernization on USS Jimmy Carter and USS North Carolina, as well as the completion of the existing TI-08 effort and the Virginia Class Block III TI-10 Large Aperture Bow (LAB) Array effort for SSN 784.

Work will be performed in Manassas, VA (90%) and Syracuse, NY (10%) and is expected to be complete by June 2009. This contract was not competitively procured by US Naval Sea Systems Command.

Nov 5/08: The Virginia Class nuclear fast attack submarine Program Office Virginia Class Sub Program Wins Acquisition Awardreceives the 2008 David Packard Excellence in Acquisition Award during a ceremony at Fort Belvoir, VA. This marks the third time (1996, 1998, 2008) that the Virginia Class Program Office has earned the award. The Virginia Class Program was recognized for excelling in 4 specific areas: reducing life-cycle costs; making the acquisition system more efficient, responsive, and timely; integrating defense with the commercial base and practices; and promoting continuous improvement of the acquisition process.

Categories: Defence`s Feeds

Italian Typhoon Jets Scrambled To Intercept TUI Fly Boeing 737 Over Montenegro

The Aviationist Blog - Wed, 10/04/2019 - 10:52
The airliner had lost contact with the Air Traffic Control, sparking the alert launch of two Eurofighters in QRA (Quick Reaction Alert). On Apr. 9, 2019, two Eurofighter Typhoon jets belonging to the 36° Stormo [...]
Categories: Defence`s Feeds

DRS Laurel Technologies to support DDG Modernization | Saab shortlisted for Finnish Squadron 2020 Program | Australia tested SMArt 155mm Round

Defense Industry Daily - Wed, 10/04/2019 - 06:00
Americas

The Air Force awarded Boeing a $91.3 million contract modification for a super high-speed computer intended to improve the F-15’s electronics warfare capability. The modification provides for the production and integration of the Advanced Display Core Processor II (ADCPII) boxes into the F-15 platform. The ADCP II is also known as Suite 9. According to Boeing, it is the world’s fastest flight mission computer, capable of processing up to 87 billion instructions per second. In 2016, the F-15E tested the flight computer during a flight on July 8 at Florida’s Eglin Air Force Base. The ADCP II is part of a wider $12 billion modernization program taking place across the range of Eagle types being flown in the USAF inventory. The F-15 Eagle is a twin-engine, all-weather tactical fighter aircraft. It is the Air Force’s primary fighter jet aircraft and intercept platform. The Eagle’s air superiority is achieved through a mixture of unprecedented maneuverability and acceleration, range, weapons and avionics.

DRS Laurel Technologies won a $53.7 million supply contract in support of the guided-missile destroyer (DDG) modernization program. The deal includes cost reimbursable services for the repair station console (RSC). According to the DoD, the RSC installation is accomplished in whole or in phases that minimize interruption in ship operating schedules while maximizing the capacity of type Commander and Naval Sea System Command agencies to upgrade and modernize hull, mechanical as well as electrical and electronic systems. DRS Laurel will deliver supplies to various Navy bases, shipyards, repair and contractor facilities. The DDG program commenced with the USS Arleigh Burke (DDG 51) in mid-2010, to provide comprehensive mid-life upgrades that will ensure Arleigh Burke class ships maintain mission relevance. With an expected life of 35 years or more, the sustained maintenance and modernization of these ships is crucial to their continued role as an essential component of surface warfare. The Navy modernization program provides a full spectrum of technical support encompassing all phases of the alteration/installation process. DRS Laurel Technologies will perform in Virginia and various other places and expects to be finished by April 2024.

The Navy contracted Hamilton Sundstrand with $11.1 million for repair of the processor signal utilized on the Super Hornets. The F/A-18 Super Hornet Block III or Advanced Super Hornet is the newest highly capable, affordable and available tactical aircraft manufactured by Boeing. The Super Hornet Block III comes equipped with Distributing Targeting Processor Network (DTP-N) and Tactical Targeting Network Technology (TTNT). These are a computer and a big data platform that work together to aid in even more efficient movement and management of data within assets. The Block IIIs sensors along with the APG-79 AESA Radar coupled to DTP-N and TTNT systems plots information on the Advances Cockpit System making it easy for aircrews to view and manage information. A key capability of the aircraft is the installation of the Raytheon AN/APG-79 multimode AESA tactical radar which has passive detection, active radar suppression modes of operation to provide air-to-air, air to ground, targeting, tracking and self-protection. This radar provides critically important data. Work will take place in Windsor Locks, Connecticut and is scheduled to be completed by April 2024.

Middle East & Africa

Local media reports that the French Army started to withdraw its troops from Iraq. According to officials, the French artillery group, which was deployed on the Iraqi-Syrian border against the Islamic State (IS) group, has completed its mission. The 150-strong Task Force Wagram, an artillery battle group armed with three Caesar 155 mm howitzers, was deployed in Iraq since September 2016 alongside the anti-jihadist coalition. French Army Caesars participated in the liberation of the Iraqi city of Mosul from the Qayarah Forward Base. They then were deployed along the Iraqi-Syrian border, near the Iraqi city of al-Qaim, in support of the Syrian Democratic Forces (FDS).

Europe

Finland shortlisted Saab as a Combat System provider for the Finnish Squadron 2020 program. The potential contract would have Saab provide and integrate the Finnish Navy’s four new Pohjanmaa Class corvettes within the Squadron 2020 program. The program is a project by the Finnish Navy. Its aim is to replace the seven vessels the Navy will decommission. Four modern corvettes will be procured to replace the vessels to be decommissioned. All of the Finnish Navy’s current vessels feature at least one system from Saab, with the majority of vessels operating several systems from Saab. According to the company, Saab has not yet signed any contract or received an order relating to Squadron 2020.

Asia-Pacific

Thales announced, that the company together with the Kalyani Group have formalized a new collaboration for the design, development and manufacture of next generation weapons systems for the Defense and Law Enforcement sectors in India and abroad. The two companies have inked an agreement for the joint venture. According to the company, the collaboration will leverage Thales’s more than 100 years of experience in the design, development and manufacture of the world’s leading defense systems. The agreement was signed onboard the HMAS Canberra.

The Australian Army successfully tested its new Sensor-fused Munition for Artillery (SMArt) 155mm round. The projectile was tested during Exercise Chimera, conducted on 24 and 25 March, at the Shoalwater Bay Training Area near Rockhampton, Queensland. The SMArt 155 is a fire and forget artillery round that is very effective in GPS denied environments and against targets with large target location errors (TLE). It uses high performance explosively formed penetrator (EFP) technology and a multi-mode sensor suite to provide predictable and precise lethal areas of effects in all weather and environments. According to the Australian Department of Defense, the SMArt 155 projectile will provide the army with the ability to effectively engage and destroy heavy armored fighting vehicles, such as main battle tanks, at operationally significant ranges, in all weather and terrain.

Today’s Video

Watch: China Third aircraft carrier taking shape in Shanghai

Categories: Defence`s Feeds

Dutch F-16 Hit By Own Bullet During Mission At The Firing Range.

The Aviationist Blog - Tue, 09/04/2019 - 21:39
Ricocheting bullets can be extremely dangerous. A Royal Netherlands Air Force F-16 was damaged during live fire training exercises at Vliehors Range on the island of Vlieland in the northern Netherlands, on Jan. 21, 2019. [...]
Categories: Defence`s Feeds

Japanese F-35 Lightning II Stealth Aircraft Reported Missing Over The Pacific Ocean

The Aviationist Blog - Tue, 09/04/2019 - 14:42
The aircraft has disappeared at around 19.27LT. The status of the aircraft and its pilot is unknown. According to several Japanese media outlets, an F-35A Lightning II belonging to the Japan Air Self Defense Force [...]
Categories: Defence`s Feeds

Saab to deliver Sea Giraffe to Canadian Navy | IWI introduces new Assault Rifle | UK sends F-35B on first Overseas Deployment

Defense Industry Daily - Tue, 09/04/2019 - 06:00
Americas

Leidos won a $19.4 million ceiling cost-reimbursement contract for system integration and field testing of a laser weapon system at Kirtland Air Force Base in New Mexico. Specifically, the deal is for the advancement of laser weapon system technology through research and development of systems as well as evaluating performance in relevant operational environments. The Air Force Research Laboratory Directed Energy Directorate at Kirtland Air Base develops technologies in laser systems, high power electromagnetics, weapons modeling and simulation as well as directed energy and electro-optics for space superiority. With its laser programs the lab is trying to achieve a laser weapon system that can operate in all flight regimes against targets that are approaching at supersonic speeds, which must be intercepted at significant range, according to a report. By 2021, the Air Force plans to test laser weapons from fighter jets to destroy high-value targets, conduct precision strikes and incinerate enemy locations from the sky. Work is scheduled to be finished by April 2022.

Lockheed Martin contracted Saab to deliver Sea Giraffe AMB 3-D surveillance radars to the Royal Canadian Navy’s two new Protecteur Class Joint Support Ships. According to a press release by Saab, the Sea Giraffe AMB will form part of the command management system for the new ships. The Sea Giraffe Agile Multi Beam (AMB) is a C-band maritime 3D mid-range multifunction radar. The radar provides airspace reconnaissance and simultaneous target tracking, weapon system targeting and high-resolution navigation. The Sea Giraffe AMB has been optimized for use on the Swedish Visby Class corvettes and the Independence Class US Coast Guard. The AMB contains a number of independent elevation-angle antenna beams. Saab will perform work in Gothenburg, Sweden and Halifax, Canada with deliveries scheduled between 2020 and 2022.

Middle East & Africa

Israeli Weapons Industries (IWI) introduced a new assault rifle during the LAAD 2019 exhibition in Brazil, local media reports. The so called Carmel is a conventional configuration rifle, which is offered in four different barrel lengths: 267mm, 305mm, 368mm and 406mm. The rifle features special steels, aviation grade aluminum and high impact polymers for high performance in small unit operations across a wide range of environments and different combat scenarios. It has a rotating bolt system and is equipped with picatinny rails on all sides to allow 100 percent compatibility with any available sights, devices or accessories. The weight of the rifle without a magazine or sight is 3.3 kg.

Europe

Britain will send its F35B aircraft on their very first overseas deployment this year. According to the British government, the aircraft will make their way from Royal Air Force home station Marham in Norfolk to Cyprus. This marks an important milestone for the F35B’s journey to become fully operational. The deployment will see personnel from the Royal Air Force as well as the Navy gain vital experience in maintaining and flying the aircraft in an unfamiliar environment. Britain currently owns 17 F-35B aircraft, and plans to procure 138 over the life of the program. The country plans for the jets to hit targets in Syria as soon as this summer, the Times reported last December.

German defense company Rheinmetall won a $122.8 million contract from the German Bundeswehr to deliver 32,000 rounds of artillery ammunition. The deal includes an option for a further 11,000 for $41.7 million. The ammunition ordered by the Bundeswehr is the 155mm DM121. At the end of March, the German parliament approved $28 million in funding for procurement of 155 mm ammunition for the Panzerhaubitze (PzH) 2000 self-propelled howitzer. The DM121 can attain ranges of up to 30 kilometres and can also be used in training as well as field exercises. According to Rheinmetall, the DM121 is capable of penetrating a several-centimeter-thick wall of reinforced concrete before detonating in controlled fashion on the opposite side. Rheinmetall Waffe Munition will produce the 155mm artillery ammunition for the five-year-contract in Unterlüß, Germany.

Asia-Pacific

According to Jane’s, South Korean company Korean Aerospace Industries started ground-based engine trials of the Light Attack Helicopter (LAH) it developed for the Republic of Korea Army. The LAH, developed around the Airbus H155 twin-engined platform, features a turreted 20 mm Gatling-gun under its nose, stub wings provisioned to carry rocket pods as well as a nose-mounted electro-optical/infrared (EO/IR) sensor, fuselage- and tail-mounted missile warning receivers, and upwards-directed exhausts for a reduced IR signature. The 214 LAHs that are currently being produced are scheduled to enter into service in 2022/2023.

Today’s Video

Watch: Here’s How F-35 Technology Would Be Compromised If Turkey Also Had the S-400 Anti-Aircraft System

https://www.youtube.com/watch?v=UAV8dMtc1A8
Categories: Defence`s Feeds

Canada’s C$ 2.9B “Joint Support Ship” Project, Take 3

Defense Industry Daily - Tue, 09/04/2019 - 05:58

HMCS Protecteur
(click to view larger)

As part of its spate of military modernization announcements issued just before Canada Day (July 1) 2006, the Canadian government issued an RFP that began the process of defining and building 3 “Joint Support Ships.” The aim was to deliver 3 multi-role vessels with substantially more capability than the current Protecteur Class oiler and resupply ships. In addition to being able to provide at-sea support (re-fueling and re-supply) to deployed naval task groups, the new JSS ships were envisioned as ships that would also be capable of sealift operations, as well as amphibious support to forces deployed ashore.

This was expected to be a C$ 2.9 billion (USD $2.58 billion) project. This article describes the process, the industry teams participating, and some of the issues swirling around Canada’s very ambitious specifications. Specifications that ultimately sank the whole project, twice, in a manner that was predictable from the outset. Leaving Canada’s navy with a serious problem, as its existing ships were forced into retirement. Will another go-round in 2012-13 help any? And what will Canada do in the meantime?

Take 2: Lessons, Process, and Contenders

Berlin Class
(click to view larger)

The 24,700t Canadian oiler and supply ships HMCS Protecteur (T-AOR-509, commissioned 1969), and HMCS Preserver (T-AOR-510, commissioned 1970) have contributed to humanitarian aid missions in Florida and the Bahamas, peace-making off Somalia and East Timor, and have been poised for the evacuation of non-combatants from Haiti, to name but a few of their recent endeavors. In the end, both HMCS Protecteur (fire) and HMCS Preserver (corrosion) were forced into “early” retirement in September 2014, after 45 and 44 years of respective service time.

Canada picked the 20,240t Berlin Class as its follow-on supply ships in June 2013, but hasn’t managed to issue a build contract. Current projections involve an expected cost of C$ 2.6 billion, for ships that Canada is unlikely to receive before 2020 at the earliest.

This outcome wasn’t necessary, but it was predictable. Meanwhile, interim leases of much larger 49,600t American ships are being considered as a bridge-buy option.

JSS Procurement Plan #1

Dutch JSS concept
(click to view full)

The ship’s requirements were unveiled in June 2006. they included the ability to carry liquid and bulk supplies, amphibious support roles, a hangar for multiple helicopters, and a strengthened hull for operations in ice. August 2008 saw the predictable demise of that JSS program (vid. Appendices A & B), but Canada’s Protecteur Class still faced all of the same issues with maintenance, and still had a limited lifespan left.

Canada’s DND was still thinking things over in January 2010 when the Dutch made a move of their own, ordering their own “Joint Logistic Support Ship” with specifications that closely matched Canada’s stated JSS needs and requirements.

Canada made no move. Its government remained stuck considering what it wanted to do, and JSS discussions became intertwined with a proposed national shipbuilding strategy that added more complexity and delay. Some countries like Australia have shifted toward a single preferred shipbuilder approach, in order to keep their defense shipbuilding industrial base alive despite limited orders. Regional politics make that a perilous option for any Canadian government, so in June 2010 Canada opted for a dual preferred shipbuilders approach. Their National Shipbuilding Procurement Strategy (NSPS) would build their future combat ships in one shipyard, and their future support and non-combatant ships at a second location.

With that step out of the way, July 2010 saw the JSS program’s re-start announcement, this time at C$ 2.6 billion instead of $2.9 billion. With the Canadian dollar close to par with the US dollar, currency shifts made up some of that difference. The other difference involved cutting the planned order to just 2 ships instead of 3, after previous program experience showed that it wasn’t possible to buy 3 ships that do all of the things that Canada wanted, for the money it was prepared to spend.

JSS Procurement Plan #2

A15 Cantabria
(click to view larger)

October 2010 saw the final piece of the puzzle fall into place. A dysfunctional political and procurement system has led Canada’s government to use ACAN buys for big defense purchases, almost all of which have been organized as rigged sole-source decisions instead of competitions. The JSS program looked to pick one of 2 existing designs that were already in service with NATO allies.

The Dutch multi-role JSS, which isn’t in service yet, wasn’t one of the 2 choices.

Contender #1 was ThyssenKrupp Marine’s 20,240t Berlin Class, with 3 examples serving in the Germany Navy. These ships are mostly conventional oiler and replenishment ships, with storage for 9,330t of fuel oil, aviation fuel and fresh water, and 550t of mixed cargo. They can carry light armament and up to 2 medium helicopters, with an on-board hospital that can handle up to 43 patients.

Contender #2 was Navantia S.A.’s Cantabria Class, an enlarged 19,500t version of the Patino Class replenishment ship. Cargo specifications for the smaller Patino are 8,480t fuel capacity (6,820t diesel and 1,660t aviation), and 500t of mixed cargo. The Cantabria carries a crew medical center with 10 beds, including a operating facilities equipped for telemedicine by videoconference, an X-ray room, dental surgery, sterilization laboratory, medical surgery and gas containment center.

While each of these ships has some minor capabilities beyond the basic fleet replenishment mission, the most striking thing about these choices is their signal that Canada had effectively abandoned its attempt to make the JSS a multi-role amphibious operations ship.

JSS Procurement Plan #3

TKMS concept
(click to view full)

Discussions were held with each firm concerning Canada-specific modifications to their designs, and the terms under which they’d be willing to hand over their designs to a designated Canadian shipbuilder. Those discussions reportedly didn’t go well, and other reports surfaced that BMT Fleet Technology of Kanata, ON near Ottawa might offer an design if those negotiations failed.

The report turned out to be true, and in March 2012, Canada gave design contracts to BMT and to TKMS. BMT would offer a custom JSS design for Canada, while TKMS would offer a modified version of the Berlin Class. Canada would pick a design between the 2 once the teams were done, arrange license production in Canada at Vancouver Shipyards per the NSPS selections, then contract with the shipyard.

Adding a new design that is not in service would vastly increase the program’s risks. On the other hand, their parent company has an Aegir family of ships that were designed from the outset to be built in “local country” shipyards, and will form the basis for the UK’s new MARS fleet tankers.

Canada’s conclusion? The entire competitive structure had been a waste of time. Implementation costs would be 15% less with an off-the-shelf design, so that was the only contender offering enough contingency funding for an executable project. TKMS’ modified Berlin Class was picked in June 2013, but construction isn’t expected to begin until at least “late 2016,” and delivery isn’t expected until 2020 at the earliest.

Supply Ship Cost Comparison: Canada vs. Britain

BMT’s MARS Tanker
(click to view full)

Canada isn’t the only country looking to reinvest in supply ships. As noted above, the Dutch are fielding a 28,000t multi-role supply and amphibious JSS support ship that’s similar to Canada’s original requirements, at a coat of around $500 million. Changing specifications in Canada have made that a poor comparison.

When it comes to simpler oiler/ supply vessels, Britain is a much better comparison. In 2002, Britain began a Military Afloat Reach and Sustainability (MARS) program to replace 11 supply ships in the Royal Fleet Auxiliary. Their program also went through a great deal of internal turbulence, including a program split in 2007. In early 2012, however, the Royal Navy placed its first MARS contract for 4 double-hulled oiler ships, which would also have the ability to transport and transfer other supplies.

While the 20,240t Berlin Class would certainly qualify for this role, Britain ended up choosing the option Canada didn’t: BMT’s Aegir design, albeit in a larger 37,000t ship. This makes for a very interesting comparison, and Britain added one more major difference: their ships would be built abroad, because even the UK’s shipbuilding facilities weren’t deemed ready, or good value for money. Instead, they chose one of the world’s leading shipbuilders, with a commercial and military history of on-time, on-budget delivery: Daewoo Shipbuilding and Marine Engineering in South Korea. The 1st ship, RFA Tidespring, is expected to enter service in 2016.

The cost differential is stunning.

Canada’s JSS program is budgeting C$ 2.6 billion for 2 ships of 20,240t each. Which means that each ship costs $1.3 billion. We’ll assume that rough parity with the US dollar continues throughout the project. We’ll also assume that the JSS project doesn’t end up with major cost overruns, even though this is a significant risk given Seaspan Vancouver’s lack of experience.

Britain’s 4 x 37,000t Tide Class MARS replenishment ships cost GBP 602 million total, or about $950 million equivalent. Which means that each ship costs $237.5 million. Their builder has a long record of solid performance, so this amount is fairly reliable.

The difference per ship = 5.47x, in order to build ships with just 2/3 the individual tonnage, and much greater risk of cost overruns or late arrival.

JSS: Contracts and Key Events 2019

Fire on board Protecteur; Both existing ships forced to retire; Lease of retiring US MSC Supply Class T-AOEs?

At-sea emergency

April 9/19: Sea Giraffe for Protecteur Lockheed Martin contracted Saab to deliver Sea Giraffe AMB 3-D surveillance radars to the Royal Canadian Navy’s two new Protecteur Class Joint Support Ships. According to a press release by Saab, the Sea Giraffe AMB will form part of the command management system for the new ships. The Sea Giraffe Agile Multi Beam (AMB) is a C-band maritime 3D mid-range multifunction radar. The radar provides airspace reconnaissance and simultaneous target tracking, weapon system targeting and high-resolution navigation. The Sea Giraffe AMB has been optimized for use on the Swedish Visby Class corvettes and the Independence Class US Coast Guard. The AMB contains a number of independent elevation-angle antenna beams. Saab will perform work in Gothenburg, Sweden and Halifax, Canada with deliveries scheduled between 2020 and 2022.

2014

Sept 23/14: Rent a T-AOE? CBC reports that Canada is considering a lease of the 49,600t Supply Class fast combat support ship USNS Bridge [T-AOE-10], which was recently inactivated by the US Navy because it costs $75 million per year to keep it in operation.

Older oilers cost about $40 million, and the new T-AKE dry supply ships cost aout $50 million, but they limit the speed of any naval group using them to under 20 knots. Carrier Strike Group transits are often 20-24 knots, and 25-26 knots is not uncommon; the Supply Class are the ships that can keep up. USNS Rainier [T-AOE-7] is scheduled to be held in reserve for another year, but current plans would also remove her from the fleet, over strenuous objections from fleet commanders.

A Canadian lease could help solve the US Navy’s problem by transferring the operating costs, while helping Canada at the same time. For the USA, the question is whether to give up control over the ships’ future usage, such as it is. If they believe the Canadians will send their T-AOEs and frigates to accompany US Navy strike groups often enough, it could still be a net plus. For the Canadians, the size difference is a big deal, because it affects required infrastructure. The USD $75 million per year operating cost could also be an issue to a military that may not have enough funds for operations under planned budgets. The good news is that crewing won’t be a big problem, since the 1960s-era Protecteur Class required almost twice as many crew as the late-1990s era Supply Class do. Sources: CASR, “The JSS Project: Delays, delivery dates, urgency, and alternatives” | CBC, “Canada’s navy looks to fill fleet gap with purchase from U.S.” | Defense News, “Canada To Seek NATO, US Support For Naval Air Defense, Resupply” | Defense News “Big Supply Ships May Get Reprieve – For Now” (July 2014).

Sept 19/14: Retired. Both HMCS Preserver and HMCS Protecteur are forced into retirement. HMCS Protecteur has never recovered from its engine fire (q.v. Feb 27/14) and collision with the destroyer HMCS Algonquin (q.v. Aug 31/13), which will also be scrapped. HMCS Preserver was found to have serious corrosion problems, and the destroyer HMCS Iroquois was scheduled for retirement in 2015 anyway, after 43 years of service.

Sources: CTV News, “Navy sending four Cold War era ships into retirement” | Nanaimo Daily News, “Navy to drop four ships, including Protecteur and Algonquin”.

Both T-AORs retire

Feb 28/14: Fire. As if its recent crash wasn’t bad enough (q.v. Aug 31/13), HMCS Protecteur suffers an engine room fire en route to Pearl Harbor, Hawaii. She is taken under tow by the American destroyer USS Chosin, but the tow line breaks in rough seas. HMCS Protecteur is eventually towed into Pearl Harbor on March 6/14 by the fleet ocean tug USNS Sioux [T-ATF 171].

About 20 crew suffered minor injuries, but the damage to the ship is more serious. the engine room and propulsion control machinery is badly damaged, and there’s fire and smoke damage to adjoining compartments. Some doubt the ship will ever sail again, and she has to be towed back to Canada after the damage assessment is complete. Sources: CBC, “Line towing fire-damaged HMCS Protecteur to Hawaii breaks” | CBC, “HMCS Protecteur towed into Pearl Harbor” | US Navy, “HMCS Protecteur, Crew Arrive Safely to Pearl Harbor” | CBC, “HMCS Protecteur too badly damaged to sail home on her own”.

Protecteur fire

2013

Berlin Class picked for JSS, but no contract; Inflation mismatch risks shortfalls; 2012 saw both existing oilers out of service; Collision with destroyer damages Protecteur.

HMCS Protecteur
(click to view larger)

Oct 11/13: More delays. There isn’t even a contract for the JSS ships yet, and the government is already admitting to reporters that Canada’s existing supply ships will need to be retired before the new Berlin Class variants can enter service over the 2019-2020 time frame. This is a new admission, and it’s so even though the polar icebreaker project will be deferred in JSS’ favor.

Senior officials are already talking about a service gap of “at least 18 months,” without even a contract in place to offer an notional end date. Shipbuilding isn’t even expected to start before “late 2016,” despite the use of a licensed design as the base Meanwhile, making JSS the yard’s first major military shipbuilding project sharply raises the odds of industrial mistakes and rework, cost overruns, and schedule failures.

Any delays will have costs and implications beyond even the JSS project, because Seaspan Vancouver doesn’t have the capacity to run both projects in parallel. Meanwhile, CGCS Louis St. Laurent will need at least $55 million in refits in order to keep operating until 2021 – 2022. Further JSS delays would force Canada to either spend more, or to field a navy with no supply ships and no icebreaker. Sources: Canadian government, “National Shipbuilding Procurement Strategy Secretariat announces Vancouver Shipyards to build the Joint Support Ships in 2016” | CBC, “Arctic icebreaker delayed as Tories prioritize supply ships” | Postmedia, “Shipbuilding schedule conflict to cost taxpayers extra $55 million”.

Aug 31/13: Crash. HMCS Protecteur collides with the Tribal Class destroyer HMCS Algonquin during a west coast training exercise. The towing exercise certainly went “dramatically wrong”, but that’s almost a tangential point. Until the damage is fixed, Canada’s Pacific Fleet has no replenishment ship – a situation that can be repeated at any time with JSS, given that there are only 2 ships planned.

The same amount of money could build 4 or more similar ships abroad, as countries like Britain have done. The difference illustrates the non-monetary cost of Canada’s chosen approach. The Globe and Mail, “Canadian Pacific navy fleet severely hampered without damaged ships.”

Collision

June 2-10/13: Calling Berlin. Canada chooses ThyssenKrupp Marine Systems’ “proven, off-the-shelf” design, based on the German Navy’s double-hulled Berlin Class Einsatzgruppenversorger (EGV – Task Force Support Ship), over a variant of BMT Fleet Technology’s Aegir that was picked as the base for Britain’s forthcoming Tide Class support tankers.

It wasn’t a features contest. Ultimately, TKMS won because Canada believed that implementation costs would be 15% less with an off-the-shelf design, so that was the only contender offering enough contingency funding for an executable project. First Marine International was used to validate construction cost estimates.

The TKMS design can carry 2 CH-148 (S-92) medium helicopters, and has less fuel capacity than the Protecteur Class, but useable fuel is closer. It seems that the Protecteurs can’t transfer their full payload without creating stability challenges, and their single-hull design’s days are numbered by maritime rules. ThyssenKrupp Marine Systems designs show a pair of MK-15 Phalanx systems mounted for defense, 1 forward and 1 aft.

TKMS will prepare the detailed design package for Vancouver Shipyards Co. Ltd to review in preparation for actual production, and part of that process will involve definition contract negotiations between Vancouver Shipyards Co. Ltd. and the Canadian government. Once these steps are complete, Canada will acquire the license for the ship design, allowing in-country production and support. Canada DND | Canada DND added background | Navy Recognition | TKMS concept: ship 3-view.

TKMS Berlin Class picked

Feb 22/13: The Canadian government offers a C$ 15.7 million trickle of contracts to Seaspan’s Vancouver Shipyard, in British Columbia. The money will be used to assess the Joint Support Ship design options, review the future CCGS John G. Diefenbaker polar icebreaker’s design, refine the design and specifications for the offshore fisheries science vessel, and produce plans for construction, material, subcontractors and labor. STX Marine is acting as the shipyard’s design partner. Public Works Canada | Seaspan Shipyards [PDF] | MarineLog.

Seaspan study contracts

Feb 13/13: JSS & inflation. Opposition parties draw attention to the 2.7% inflation rate being used to cost the “C$ 2.6 billion” Joint Support Ship project, and to an internal DND audit that cites 3.5% – 5.0% as the norm for the shipbuilding industry. American defense planners have been known to use even higher figures. Public Works Minister Rona Ambrose defends the estimate as coming from their usual process, but doesn’t explain the deviation from industry norms.

Over the course of a long project, the difference can add up to tens or even hundreds of millions of dollars. Which means either higher defense spending, cuts to the project, or cancellation of other projects. Higher defense spending is unlikely any time soon, and it’s hard to cut a 2-ship project. The situation could become even worse if other NSPS projects pick up the same flawed estimate, but the inflation rate issue is likely to surface again later in 2013, when the Parliamentary Budget Office tables their report on the JSS program. Canada.com

Feb 13/13: Out of action. Canada.com reports:

“National Defence reported late last year that biggest challenge facing the navy in 2012 was when its two support ships, the HMCS Protecteur and Preserver, went into maintenance at the same time…. because of their absence in late 2011 and early 2012, the navy was forced to turn to allies for help replenishing other Canadian vessels at sea until the re-supply ships came back online.”

Both oilers down

2010 – 2012

Canada launches 2nd JSS attempt, which sinks. Try plan #3?

HMCS Preserver
(click to view full)

Dec 6/12: PBO denied. Parliamentary Budget Officer Kevin Page is denied when he asks to see the winning NSPS shipyard bids, as part of a study examining the financial implications of the Joint Support Ship, and a similar effort focused on Canada’s project to build Arctic patrol vessels. From Canada.com:

“Public Works has provided PBO with some information related to the national shipbuilding strategy, including a number of agreements and reports related to Seaspan’s Vancouver Shipyards for the resupply ship study…. In a letter to Page dated Dec. 3, d’Auray indicated the winning bids were not relevant to the PBO study because they “do not stipulate awarding contracts, and the bidders were not asked to submit cost estimates for any of the vessels.”

Oct 19/12: Infrastructure. Part of the NSPS involved meeting a “target state” level of efficiency, as set by First Marine International standards. The ability to reach this state, and to finance the required upgrades, was an important part of the bidding process. Along those lines, Vancouver Shipyards holds a ground breaking ceremony as part of their C$ 200 million infrastructure investment: 4 new fabrication buildings, a shipbuilding gantry crane, and a load out pier.

While the government touts the investment as having “no cost to Canada,” Costs will be passed through one way or another. Especially when the shipyards in question are now sole-source bidders. The more likely result is that they’ll soak the provincial government for most of the funds, as their east coast counterparts at Irving did. Government of Canada

March 8-12/12: JSS Plan #3. Canada has moved forward with a new JSS approach, awarding relatively small design contracts for a custom JSS design from BMT, and a modified off-the-shelf Berlin Class design. Canada intends to pick a winner, and then license the design for construction in Canada.

BMT Fleet, who designed Britain’s new 37,000t MARS fleet tankers and supply ships, is awarded a 12-month, C$ 9.8 million design project to further develop their Contract Design as a JSS option. They have already done a JSS Preliminary Design under earlier contracts, and have been supporting the JSS project since December 2002 through a series of individual taskings issued under an Engineering, Logistics, and Management Support (ELMS) Services Contract. These have included a broad range of engineering and design studies.

At the same time, ThyssenKrupp Marine Systems has won an undisclosed contract to modify their Berlin Class Task Group Supply Vessel (EGV) to meet Canadian requirements. The modified design will be developed by ThyssenKrupp Marine Systems Canada (TKMSC) and TKMS subsidiary Blohm + Voss Naval. If the modified Berlin Class EGV design is chosen, it would be followed by a functional design contract, and those designs would be licensed for construction by a Canadian shipyard. This design contract includes initial provisions for a licensing agreement to that effect. Blohm + Voss | BMT Fleet.

New JSS approach, initial design contracts

Nov 4/11: HMCS Preserver crash. As it prepares to return to service following a C$ 44.7 million refit, HMCS Preserver hits the floating drydock at Irving’s shipyard in Halifax, NS. The drydock now has a hole, and the ship’s hull is reportedly dented above the water line.

The incident underscores the vulnerability of Canada’s fleet to problems with existing supply ships, and the importance of the future JSS. Until HMCS Preserver is returned to service, HMCS Protecteur will remain Canada’s only supply ship. Which it did – until it had to go in for repairs in 2012, leaving Canada with nothing. CBC | Global TV News | Ottawa Citizen’s Defence Watch.

HMCS Preserver crash

Oct 19/11: Trouble. The National Post reports that the JSS program has hit a major block:

“Defence sources said it is in trouble because two companies competing to design the new ships – ThyssenKrupp Marine Systems of Germany and Navantia S.A. of Spain – are backing away from the bidding process. It is understood that the government is not prepared to pay their asking price and is likely to turn to a domestic Canadian design being prepared by engineering support contractor BMT Fleet Technology of Kanata, Ont. None of the competing companies responded to requests for comment Tuesday… One Defence insider said the JSS problems reflect a lack of experienced procurement staff. “This is so depressingly Canadian – you go out to bidders, you indicate an interest in designs, you load on extras and then say ‘no, thank you.’ It could set us back another five years,” he said. The new supply ships were due to be in service by 2017 but sources say that deadline is unlikely to be met now.”

Bidders not playing

Oct 19/11: NSPS. Tim Colton’s Maritime Memos was right, it took just over a year from Canada’s government to announce the obvious. In their partial defense, there was a May 2011 election in between, and at least they didn’t pick an obviously disastrous political choice for the 20-30 year, C$ 33 billion program.

On the west coast, Seaspan subsidiary Vancouver Shipyards Co. Ltd. in North Vancouver, BC wins the C$ 8 billion non-combat portion. They will build the 2-3 Berlin or Cantabria derivative JSS support ships, 4 off-shore science vessels for the Coast Guard, and a new polar icebreaker, for a total of 7-8 ships, worth about C$ 8 billion. Despite the JSS’ long-running competition, and the fleet’s need, the 3 off-shore fisheries and 1 oceanographic science vessels will be the first ships built. Other team members include and Alion Canada (design), CSC (logistics), Imtech Marine (ship systems), STX Canada Marine (design), and Thales Canada (ship systems).

There are 2 caveats worth noting. One is that the projects will involve 100% value industrial offsets, which matters because many ship systems and components, especially combat-related equipment, will come from outside Canada. The other is that the government can take over the shipbuilder if it signs up for NSPS, and then defaults on contractual obligations (vid. Part 3, Section 5.2). Read “Canada’s National Shipbuilding Strategy” for full coverage.

NSPS shipyards designated

Oct 8/10: NSPS. Public Works Canada announces the results of their initial shipbuilding strategy Solicitation of Interest and Qualification. One yard will be selected to build combat vessels, while a 2nd yard will build non-combat vessels. Five Canadian shipyards have been short-listed. Read “Canada’s National Shipbuilding Strategy” for full coverage.

Oct 8/10: RFI. Canada’s MERX government procurement board posts solicitation W8472-115312/A. It says the government has approved a new approach, restricted to “adapting the designs of recently built naval fleet replenishment ships that are operating with other NATO Navies.”

It then narrows the contenders down to ThyssenKrupp Marine Systems’ Berlin Class, and Navantia S.A.’s Cantabria Class. The process will begin by ordering risk reduction studies to cover adapting these designs to meet Canadian requirements, provide historical costs of building, and deliver a proposal that includes a data package and technology transfer agreement so a Canadian shipyard can build and support the ships. If one of these designs is selected for the JSS, Canada will amend the contract with that designer to implement its proposal.

RFI for v2.0

July 14/10: JSS, Take 2. Canada’s Department of National Defence (DND) issues background materials concerning a second attempt at the JSS project. Specifications are very, very thin. The second go-round is listed as a C$ 2.6 billion project, though currency strength would offset some of the $300 million reduction. So would the revised plan of buying 2 ships, with an option for a 3rd.

Canada’s proposed shipbuilding strategy fits into the plan, but a construction bid can’t be expected before 2012 at the earliest. The mission description is close to meaningless, and will remain so until tradeoffs are specified among these capabilities, and exact requirements become clearer:

“The primary role of the JSS will include supply of fuel, ammunition, spare parts, food, and water. The JSS will also provide a home base for the maintenance and operation of helicopters, a limited sealift capability, and logistics support to forces deployed ashore… the [current] definition phase, will involve the assessment of both new and existing designs. Existing ship designs are those already built, operating, and meet key specific Canadian requirements. A new ship design is being developed by government and industry officials working side-by-side… The design is expected to be available in approximately two years, at which time a Canadian shipyard, selected as part of the National Shipbuilding Procurement Strategy, will be engaged to complete the design of and build the Joint Support Ships.”

See: Backgrounder | Release.

2nd JSS procurement attempt begins

June 3/10: NSPS. Canada announces a new shipbuilding strategy:

“Two shipyards will be selected to build the large vessels (1000 tonnes displacement or more)… process, led by Public Works and Government Services Canada (PWGSC)… will result in the signing of formal agreements establishing a long-term relationship between each yard and the Government of Canada. The negotiation and signing of umbrella agreements with the successful shipyards is expected to occur in the 2011-2012 timeframe.

One shipyard will be selected to build combat vessels. This will enable the procurement of the Canadian Surface Combatant [CSC frigate/destroyer replacement] and Arctic/Offshore Patrol Ships (AOPS)… Another competitively selected shipyard will build non-combat vessels, such as the Joint Support Ships (JSS)… Shipyards among those not selected for the building of large vessels may be engaged in the building and support (maintenance, refit, and repair) of the approximately 100 smaller vessels included within the strategy. Maintenance, refit, and repair of the Navy’s fleet represent some [C$] 500 million annually.”

Now it has to start picking winners, and approving programs. Major ministry participants include Defense, Public Works, and Fisheries & Oceans. Plus Industry Canada. Not a recipe for speed. DND release | Public Works | Coast Guard.

National shipbuilding strategy announced

Jan 18/10: Dutch JSS. The Dutch go ahead with their own multi-role “Joint Logistics Support Ship” program, with a budget of EUR 385.5 billion for 1 ship. Could this represent a JSS contender if the project resurfaces?

2006 – 2009

JSS program launched, contracts signed, then program canceled.

JSS v1.0
(click to view larger)

April 13/09: Rust-out. Canadian Broadcasting Corporation News obtains copies of the Canadian Forces’ 2009-2010 Maritime Staff Capability Plan, in which navy Commodore Kelly Williams warns that maintaining the Navy’s existing 40 year-old supply ships will be problematic:

“Maintaining the obsolescent tankers is costly and will put further pressure on the already constrained [repair budget] and further delays in the mid-life refit for Halifax class [frigates] which will lead to rust-out…”

“Rust-out” is caused by repeatedly sanding warships, which leads to hulls becoming thinner and more fragile. CBC News quotes Liberal Party (official opposition) Senator Colin Kenny, who chairs the Senate’s standing defence committee, is highly critical of the program, which was begun under one of his own party’s governments:

“The navy only asked for three [ships] when it knew it needed four,” he told CBC News. “But the costs have come in that there’s only enough money for two. And if Mr. MacKay thinks things are on track, he really doesn’t know what’s happening.”

April 2/08: The Ottawa Citizen publishes an op-ed, “Celebrating a robust navy with an uncertain future.”

Aug 22/08: JSS – The End. Canada’s Ministry of Public Works and Government Services announces the termination of the JSS program:

“After receiving and evaluating the mandatory requirements for the Joint Support Ship Project from the bidders, the Crown has determined that the proposals were not compliant with the basic terms of the Request for Proposals (RFP). Among other compliance failures, both bids were significantly over the established budget provisions… The Department of National Defence and the Department of Fisheries and Oceans are currently considering the next steps. The government is committed to procure, repair and refit vessels in Canada according to the government’s Buy Canada policy.”

The Hill Times was blunt, as it offered more background details:

“According to industry insiders, both design teams were unable to come up with a ship design under-budget. Although details are tight, officials say one team submitted a blueprint for two vessels [instead of 3], while the other sent in a plan for three, which was way over budget. In other words, industry has sent a strong signal to Ottawa – either increase the funding or scale down the project.”

The government’s decision left the Canadian navy’s future ability to operate independently at risk. HMCS Preserver and HMCS Protecteur were expected to reach the end of their service life between 2010- 2012, but the failure of the JSS concept means that it will be very difficult to build replacement ships before that date. Meanwhile, HMCS Preserver is headed into dock to have its boiler system repaired, just 2 years after the last repair. Those systems are an ongoing risk, as the Canadian Press explains:

“An undated briefing note, leaked to The Canadian Press over the weekend, show the navy was bracing for the blow… “If the Protecteur and Preserver are going to be needed longer than expected, we will also determine what needs to be done to keep our supply ships safe, operational and available until they can be replaced… Many of their systems are nearly obsolete, such as the boilers they use to generate steam for main propulsion. As you might expect, it’s becoming increasingly difficult and costly to maintain these ships. Spare parts are no longer readily available, and the skills needed to operate and maintain systems that were already mature in the 1960s are becoming increasingly rare.”… Beyond basic mechanics, marine engineering designs and environmental laws have become more complex over the last 40 years. The navy’s two supply ships are single hull designs…”

See also: The Hill Times | Globe & Mail | Canwest News Service | Canadian Press | CBC.

JSS terminated

Aug 3/08: The National Post reports that discussions have begun with Dutch shipbuilders, in the wake of serious problems with the JSS bid. The Netherlands builds the highly-regarded Rotterdam Class LSDs – but political friction is building around the prospect of contracting for shipbuilding outside Canada. Even though…

“This year, the federal government determined that proposals from two Canadian consortiums earmarked to build the new fleet were “noncompliant.” Defence officials were told the Joint Support Ship budget was not enough to build the three vessels envisioned and attempts to obtain more funding from the government have been unsuccessful.”

See Apendix A, which discusses why this outcome could have been, and was, predicted long in advance. Meanwhile, Conservative Party Defence Minister Peter MacKay’s press secretary Jay Paxton is attempting to douse the flames of controversy regarding the Netherlands visit:

“Although the director-general of major project delivery land and sea was in Europe on other business, he had a chance to meet with government representatives from the Netherlands who are undertaking a similar project and they compared best practices in the context of an update on their project.”

May 19/08: The Ottawa Citizen reports problems with the JSS program:

“The $2.1 billion set aside for buying three Joint Support Ships is not enough, defence officials confirm. They point out that part of the problem is the new vessels would conduct missions far beyond the scope of re-supplying warships at sea, the role now done by the decades-old Protecteur-class ships… There is no similar type of ship in the world, as most navies use two types of vessels to perform the distinct roles.

Defence officials have heard from industry that the money set aside by the government might be enough for two ships, not three.”

Nov 24/06: Phase 2 contracts. The Phase 2 Project Definition contracts have been awarded. Teams led by ThyssenKrupp Marine Systems Canada Inc. and SNC-Lavalin ProFac Inc. were selected, receiving identical contract of C$ 12.5 million (US$ 11 million). Irving Shipbuilding and BAE were eliminated. Each team will now have 14 months to develop a preliminary system specification, and a proposal for project implementation. A winner will be selected in 2008, and delivery of the first ship is planned for 2012. See MarineLog report.

Phase 2 definition contracts

June 26/06: JSS announced. Liberal Party Minister of National Defence Gordon O’Connor, Minister of Public Works and Government Services Michael Fortier and Chief of the Defence Staff General Rick Hillier announce the C$ 2.9 billion Joint Support Ship project for Canada’s Navy. This project includes a base cost of C$ 2.1 billion, plus an estimated C$ 800 million in contracted in-service support over 20 years. DND Backgrounder | DND Release.

Joint Support Ship program announced

Appendix A: The JSS v1.0 Procurement Process

JSS concept
(click to view larger)

Here’s how the three-step process announced by Paul Martin’s Liberal Party government in 2006 was expected to work:

Four industry teams were pre-qualified to compete for the contract. A request for proposals, to be issued shortly, will trigger the process to select two industry teams for the project definition phase.

The second phase, Project Definition, would see 2 qualified consortia selected from among the qualifying proposals. These two consortia will each be awarded a C$ 12.5 million contract to produce and deliver an implementation proposal consisting of a preliminary ship design, a project implementation plan, and an in-service support plan. These proposals will be evaluated on the basis of compliance and the proposal demonstrating the best value, taking into consideration technical merit and total ownership cost, will be selected as the winner.

The final phase, Project Implementation, will see the winning bidder awarded two separate but inter-related contracts. The first will be for the completed design for and construction of the Joint Support Ships. The second will be for the in-service support for the life of the vessels. Delivery of the first ship is targeted for 2012.

The expected overall project cost for the JSS includes a base cost of C$ 2.1 billion (USD $1.87 billion), plus an estimated C$ 800 million (USD $712 million) in contracted in-service support over 20 years. Industry teams were led by:

  • Irving Shipbuilding
  • BAE Systems (Project) Limited (BAE Systems Naval Ships)
  • ThyssenKrupp Marine Systems AG
  • SNC-Lavalin Profac Inc.

A list of the required capabilities could be found in the Canadian government’s detailed 2006 release. Supply functions, medical care, repair facilities, self-defense, roll-on roll-off, lift-on lift-off helicopter operation, ice capabilities, deck space for vehicles… the list goes on. All in a 200m/ 28,000t ship:

  • The provision at sea of fuel, food, spare parts, and ammunition. Goal is to enable a Naval Task Group to remain at sea for up to 6 times longer than would be possible without these ships;
  • Afloat support to Canadian forces deployed on shore;
  • The ability to navigate in first-year arctic ice up to 0.7 m thick;
  • 20 knots sustained speed;
  • A covered multi-purpose deck space for vehicles and containers with space for additional containers on the upper decks. Total of 1,000 – 1,500 lane meters desired on upper and lower decks;
  • Ability to carry 7,000t – 10,000t of ship fuel,650 – 1,300t of JP-5 naval aviation fuel, and 1,100 square meters of ammunition.
  • The operation of 3-4 maritime helicopters per ship, with rapid reconfiguration possible should the ship wish, for example, to use its hangars for evacuated disaster survivors;
  • Roll-on Roll-off (RO-RO) of cargo;
  • Lift-on Lift-off (LO-LO) of cargo.

Other capabilities would include:

  • The ability to function as a Joint Task Force HQ
  • Work and living space for additional personnel, over and above the standard crew of up to 165 people;
  • Modern medical and dental care facilities, including an operating room for urgently needed operations;
  • Repair facilities and technical expertise to keep aircraft and other equipment functioning; and
  • The ship will be configured with both active and passive self-defence systems

The new Conservative Party government kept the JSS program, and followed the competition procedure to narrow the contest down to just 2 bidders: ThyssenKrupp Marine Systems AG, and SNC-Lavalin Profac Inc.

In the end, however, the specifications, design, and budget simply could not be made to agree. The JSS project is currently in limbo. A solution is required, and soon, but successfully executing one demanded a rethink of the project’s main premises.

Surprisingly, the project got exactly that. The next iteration featured an overarching national shipbuilding strategy, and a specification set that scrapped the multi-role requirement in favor of a slightly-modified variant of a serving NATO support vessel.

Appendix B: DID Op-ed/Analysis (June 30, 2006)

HMAS Collins launch
(click for alternate view)

Candidly, the record for small to mid-size powers attempting to develop new military technologies is not all that good. Engineering is a challenging art at the best of times, and military projects are more demanding than most because of the myriad of parts to integrate and the advanced (and hence often new and unproven) nature of the technologies. Add local unfamiliarity into the mix, and the result is inevitably schedule slips and cost overruns – often significant slips, and major cost overruns.

Given the limited procurement resources of small to medium powers, such projects can easily threaten to swallow entire service procurement budgets. Cancellation means millions or even billions of dollars has been flushed down the toilet. On the other hand, continuing the program may break one’s military as other areas are starved to pay for it – all with no guarantee of success.

Australia’s Collins Class subs, for instance, are excellent vehicles. Yet cost overruns have measured in the hundreds of millions, remediation is not yet finished, and the schedule for full deployment has slipped by years. All for vessels of a well-understood ship type, based in part on a pre-existing class (Sweden’s Gotland Class), and built in cooperation with an experienced, world-leading firm in submarine technology.

Overall, the Collins Class is an example of a successful local to medium power project to develop an advanced military platform despite previous inexperience.

Canada’s Joint Support Ships, in contrast, conform to no known ship type in their breadth of required functions, and are based on no pre-existing class. The firms competing for the design are not world leaders in similar ship classes like amphibious assault ships or LPDs. Nor does the depth of Canadian design and build experience in related efforts give cause for optimism; quite the reverse. Indeed, the JSS’ breadth of functions alone suggests a difficult project for any entity or country to undertake, and little hope of much beyond mediocrity in all functions due to the required trade-offs.

The Canadian Forces may succeed in the end, and if DID would be happy to apologize. Indeed, we would be pleased to run an article here explaining why they believe they can succeed, and what steps they have taken to address their approach’s inherent risks and performance trade-offs.

For the project’s critics appear to have the high ground when they suggest that JSS is set up to become a budget-eating failure, and recommend that Canada replace the unwieldy JSS idea with a conventional oiler or two plus a few HSV rapid deployment vessels like the ones the USA is gravitating toward. Or recommend the LPD-17 San Antonio Class amphibious support ship as an alternative. Or even recommend a larger number of smaller Dutch/Spanish Rotterdam Class LPDs, plus the USA’s versatile new T-AKE supply ships.

Those kinds of risk reduction strategies would leverage successful R&D efforts, and spend more money on cutting steel and floating boats. As opposed to pursuing paper visions that risk sucking up vast resources and producing inferior products – or no products as all.

Additional Readings Canada’s NSPS and the JSS

Related Ships

News & Views

Categories: Defence`s Feeds

Why the Taleban Should Read the Afghan Constitution

The Afghanistan Analysts Network (AAN) - Tue, 09/04/2019 - 04:00

As talks between the US and the Taleban move forward, we are starting to see the contours and obstacles to peace in Afghanistan. One of the possible obstacles to reaching an agreement is the Taleban’s view that Afghanistan’s current constitution is unsuitable and unacceptable. Ghizaal Haress, a prominent Afghan lawyer and a member of the Independent Commission for Overseeing the Implementation of the Constitution, takes a closer look at the Taleban’s position and discusses how this relates to the realities of Afghanistan’s constitution and how it was arrived at.

During the February meeting in Moscow, Taleban representative Sher Mohammad Abbas Stanikzai highlighted the constitution of Afghanistan as a major impediment to peace. He labelled it “the constitution of the Kabul Administration” and dismissed it as invalid, copied from the West, imposed on a Muslim society, and arbitrarily implemented. According to the Taleban, for the constitution to be acceptable to them it must be based on Islamic principles, national interests and historical achievements. It must also ensure human dignity, national values, social justice and human rights, as well as guaranteeing Afghanistan’s territorial integrity. The draft of such a constitution, he added, should be prepared by autonomous Afghan scholars in an atmosphere of freedom.

As a commissioner on the Independent Commission for Overseeing the Implementation of the Constitution, I would be the first to acknowledge that Afghanistan’s constitution has numerous shortcomings and challenges to its implementation. However, I believe, the Taleban are wrong on multiple counts regarding the Afghan constitution. I will argue below that the constitution is in fact a constitution of the Afghan People, that Islamic principles have been written into the very fabric of the document, and that what the Taleban consider its vagueness, in fact provides necessary flexibility for interpreting and adapting the document. I finally make the case that rather than discarding this historical achievement, it would be much better to find ways to bridge our political differences within the framework of the current constitution.

A constitution of the Afghan people

The constitution of 2004 is in many ways unique compared to all its predecessors. With the exception of the constitution of 1964, all previous Afghan constitutions were drafted as a result of regime change, and were used to consolidate the power of the new ruler. Public participation was a missing element in the formulation of all these constitutions, with the Jirgas that approved them being mostly appointed. These constitutions were thus made and endorsed by a circle of people close to their rulers, without the involvement or consensus of the wider population. Therefore, these constitutions did not endure when these regimes changed, as the people – often disillusioned – saw them as the tools of failed administrations, rather than a constitution by and for the people.

In this long view, the 2004 constitution cannot simply be seen as “of the Kabul Administration”, since its formation between 2002-2003 was the most rigorous and consultative in the history of Afghanistan. The process, outlined in the Bonn Agreement, was led by Afghans. The process took 18 months and was led by two commissions – the Constitutional Drafting Commission and the Constitutional Review Commission – comprised of Afghan experts (with 9 and 35 members respectively) that drafted and reviewed the draft constitution. It included travel to the then-32 provinces, and two neighboring countries (Iran and Pakistan) to consult with the Afghan diaspora and an electoral college of 19,000 people. They, in turn, elected 502 Loya Jirga members who discussed and approved the constitution. This makes it one of the earliest and biggest achievements of the post-2001 generation.

An informal men’s caucus at the 2003/04 Constitutional Loya Jirga. Photo: Thomas Ruttig/2003

The Constitutional Review Commission, over the course of two months, managed to run an unprecedented public consultation. As described in this UN Report, the commission initiated the public consultation after a month-long awareness campaign on the role and importance of the constitution. The report indicates that “178,000 Afghans, 19 per cent of whom were women, participated in more than 556 meetings to discuss the draft. In addition, over 50,000 written surveys were submitted.” According to the International Crisis Group, the commission solicited views of people from various backgrounds and walks of life, including “elders, ulema (Islamic scholars), women, business groups, youth groups, Afghan employees of NGOs and international organisations, and former Emergency Loya Jirga delegates.”

The public consultation process also included institutions and individuals taking the initiative to present their recommendations and concerns to the constitution-making entities. In 2003, hundreds of institutions and associations, as well as numerous individuals, presented written submissions to the Commission. I remember how my office at the time, Global Rights, facilitated a process whereby a group of 40 judges, lawyers and prosecutors held several discussions, and then presented their collective views to the Constitutional Review Commission.

Public participation has many strategic advantages. I would, however, like to focus on two in this piece. First, participation and consultation reinforce the legitimacy of the constitution as “the people’s constitution.” Second, they lay the foundations for the acceptance and respect of the prospective constitution by citizens. Thus, public consultation empowered the Afghan people to engage in the making of their constitution and allowed them to participate in the public affairs of their war-torn country. This enhanced the legitimacy of the document, ensured its broad consensus and endurance and left less space for grave disagreements in the years to come.

The implementation of the public consultation faced a number of challenges (as described in the ICG report), including inadequate public education, the absence of a draft constitution during the consultations, and uncertainty around the use and incorporation of the comments into the final draft. Nevertheless, despite minimal experience, resources and the availability of technological facilities, the process was kept open to recommendations and submissions, and the commission reached out to a vast number of Afghans, as well as the diaspora in Iran and Pakistan, and brought back common insights and concerns to the commission in Kabul. The Commission may not have had time to process all the data or to systematically use it in the final draft, but the fact that the commission reached out to people, and was accessible to all citizens, made it an inclusive and participatory process that was broadly hailed by the Afghan people.

Islam in the Afghan constitution

The Taleban claim that the constitution is not based on the principles of Islam; however, Islamic principles and values are written into the fabric of the constitution. The very first two articles of the constitution define Afghanistan as an Islamic Republic and recognize Islam as its religion. Article 3 proscribes laws that contravene the tenets and rulings of Islam in Afghanistan. (1) Articles on education require the state to focus on developing religious teachings, regulate and improve religious institutions, including mosques, and devise educational curricula that includes the tenets of Islam. (2) The constitution requires presidential, and vice-presidential candidates to be Muslim, and to obey and protect the religion of Islam. (3)

On the judicial front, the constitution requires members of the Supreme Court to ensure justice in accordance with the tenets of Islam. It also obligates judges to apply provisions of Hanafi or Shi’a jurisprudence (as applicable) while deciding on cases, in the absence of relevant provisions in the Constitution or other laws. (4) The constitution guarantees the right to form political parties, but prohibits their manifesto or charter to contravene the religion of Islam. (5) The combination of these provisions enshrines Islam as the bedrock of the state.

An Afghan or a western document?

The Taleban’s claim that Afghanistan’s constitution has been copied from the West is part of a wider view that often dismisses the progress of the last fifteen years as “western” in nature. This argument is often presented without much rigour and, for the 2004 constitution in particular, the argument does not hold. The 2004 constitution drew heavily on the 1964 constitution, so much so that it created disputes within the drafting and review commissions, with some arguing that Afghanistan should adopt more modern constitutional provisions, rather than going back to a constitution adopted 40 years before. The structure and powers of judiciary and parliament, as well as the fundamental rights provisions, all have strong similarity in content and wording with the 1964 constitution.

Western influence and cooperation

While I claim that the constitution was Afghan-made and led, it can be argued that this was offset by the fact that there was considerable international influence and cooperation in the process. Decades of war and political turmoil in the country, particularly between 1992 and 2001, had left Afghanistan devastated. The state’s institutions and infrastructure were largely destroyed, poppy had become the main cash crop and a major driver of the nation’s economy, formal legal and judicial institutions became dysfunctional, and women were systematically denied their basic human rights.

Given how the country was left shattered in 2001, there was great need for international support, as recognized by both Afghans and the administration of the time, to rehabilitate state institutions and begin processes for social and political development in the country. Without international support, the broad-based constitution-making process would never have been realised. While in an ideal situation, Afghans would have wished to see the process solely handled by Afghans, dependency on foreign aid left Afghanistan reliant on donor countries.

Notwithstanding the claims of intervention in the process, there is little evidence of direct international influence in the substance of the constitution, particularly none that goes against accepted social and religious norms. For instance, during the drafting of the Afghan constitution there were international technical advisors, but their role was minimal. The Afghan members paid little attention, if at all, to their international and comparative expertise, as they wished to maintain Afghan ownership of the process. One of the advisors, Professor Yash Pal Ghai, an internationally renowned constitutional lawyer from Kenya, who I met in 2015 in Budapest, told me how underutilized he had been at the commission. The commission and its leadership largely ignored the discussion papers that were written by Ghai and his international colleagues.

Fundamental rights

One of the issues that the Taleban particularly tend to associate with the influence of the international community is the issue of human rights. It is true that there were efforts by the international community to ensure that the new constitution would safeguard fundamental rights. However, in view of the widespread violations of human rights and women’s rights in the period before 2001, this was obviously not a purely international concern. A large number of national organisations, including the members and secretariat of the Constitutional Review Commission, were heavily involved in demanding better protection of fundamental rights, particularly those of women and minorities. It would be unjust to argue that human rights were only a concern of the international community and that Afghans did not voice their concerns after decades of violations of their rights.

Women delegates sat separately during the the Constitutional Loya Jirga of 2003/04 (left to right: Suraya Parlika, unknown, Massuda Jalal). Photo: Thomas Ruttig/2003

One should also look back at the previous constitutions of Afghanistan, and assess the scope of fundamental rights. Starting from the constitution of 1923, every subsequent constitution in Afghanistan has had provisions with regard to fundamental rights. For instance, the constitution of 1923, among others, upheld the equal rights and obligations of Afghan citizens, guaranteed human liberty and abolished slavery, guaranteed freedom of the press, and prohibited torture. Furthermore, Afghanistan, as a member state of the United Nations, had international obligations with regards to the rights and liberties of its citizens.

Listing the specific rights enshrined in the constitution and discussing how they reflect the realities, history and obligations of Afghanistan with regard to its international commitments, is beyond the scope of this article. However, it is noteworthy, that these fundamental rights were not imposed on Afghans, but were rather reinforced, in response to past systematic violations and breaches.

It is also important to note that constitutions serve as the guarantors of fundamental rights, and not as the imposers. It is for citizens to decide how they wish to enjoy and practice these rights. In other words, the constitution guarantees citizens’ rights, but does not inflict them on them. As an example, a citizen’s right to vote is guaranteed by the constitution, to ensure that the government does not deprive the person of this right. However, the citizen has the freedom to choose whether to exercise this right or not.

On the other hand, the Afghan constitution explicitly recognises its own supremacy over international treaties and covenants, and requires their conformity with the constitution. (6) International scholars as well as a body of literature have repeatedly pointed out the constitution’s weakness of provisions on international law, and its lack of strong provisions to ensure Afghanistan’s commitments to its international obligations. The Islamic provisions of the constitution, in contrast, are much stronger than those on international law and human rights: where the former has received extensive attention, the latter has not. The constitution thus presents moderate language on international treaties and human rights documents, and requires the state to ‘observe’ them, as compared to Islamic provisions that ‘obligate’ the state.

Vagueness or flexibility?

Where the Taleban claim there is vagueness in the constitution, I would argue that there is necessary flexibility. When constitutional drafters write constitutional provisions, they leave gaps and ambiguities, both intentionally and unintentionally. The latter is due to the inability of the drafters to foresee all possible scenarios that may arise in a constitutional regime. The former is to leave room for innovations and reforms; providing law makers with the ability to adapt to needs of the time. Constitutions also prescribe methods for amendments to be made where provisions are unclear, contradictory, need further details, or need to be changed.

There are indisputably ambiguities and gaps in the constitution of 2004. But it is not unique to Afghanistan. When the current constitution of the United States was drafted, it did not include any provision on fundamental rights. The rights of citizens were included in the US constitution through amendments.

The Afghan constitution describes three categories with respect to amendments. First, provisions that cannot be amended: the principles of Islam and Islamic Republicanism. Second, provisions that can be amended conditionally: amending fundamental rights of the citizen, on the condition that the intention is only to strengthen them. Third, the amendment of anyother provision with respect to new requirements of the time. (7) The constitution also presents the mechanisms for constitutional amendments, which would allow for the refinement of outstanding and significant ambiguities or points of contention.

A constitutional amendment process can be initiated at the proposal of the president or a majority of National Assembly members. In order to process the amendment, a commission will be established to prepare a draft proposal. The commission will have members from the government, National Assembly and Supreme Court. At the third stage, the Loya Jirga will be convened to approve the amendment (with a two-thirds majority). The amendments come into force after endorsement by the president.

Conclusion: Better to bridge political differences without discarding the constitution

The constitution making process was not perfect. There were flaws and shortcomings. Likewise, there are gaps and limitations in the substance of the constitution that have posed challenges to its implementation during the last 15 years. There have also been instances of violations and extra-constitutional acts. However, given how shattered the country was at the time, it was arrived at through an imperfect but democratic process. Like all other constitutions, the Afghan constitution reflects an ambition for its society to struggle towards, for its government to uphold, and for its citizens to be able to hold their governments to account. What matters most is the political will to uphold the constitution. In the absence of any commitment to the rule of law and constitutionalism, no constitution, however well-drafted, can help a government succeed.

A constitution may be written in the best way possible, but still not be implemented. The constitution of North Korea is a perfect example of a constitution that protects the rights of its citizens on paper, but not in practice. On the other hand, a constitution may be written with shortcomings and gaps, but if there is a political will to uphold the principles of constitutionalism, it can be best practiced.

What makes the Afghan constitution of 2004 different and worth retaining, is its inclusiveness. It combines and reconciles Islam, democracy, pluralism, human rights and social justice; a combination that is unprecedented in Afghanistan.

The Taleban say they envision a constitution based on Islamic principles, national interests, historical background, social justice, human dignity, and human rights. While these principles and values are explicitly enshrined in the Afghan constitution, the Taleban claim they are not. It is understandable that the Taleban would like to see changes in the constitution; however, the current constitution is open for amendment, in order to remain a living document and one that can respond to the emerging needs and demands of society.

There will remain deep ideological divisions within Afghanistan, regardless of our constitution. Our history shows that creating a new constitution will not solve this. It is important to note that people of different political backgrounds came together and agreed on this law, endorsed it, accepted it, and respected its provisions. In doing so, they built broad consensus and vested the highest level of legitimacy in the constitution, more than any legal document ever has in Afghanistan. Therefore, rather than throwing out this constitution and creating a new one, it would be better to find ways to bridge our political differences without discarding this truly historic achievement.

Ghizaal Haress is a commissioner of the Independent Commission for Overseeing the Implementation of the Constitution

 

(1) Article One. Afghanistan shall be an Islamic Republic, independent, unitary and indivisible state.

Article Two. The sacred religion of Islam is the religion of the Islamic Republic of Afghanistan. Followers of other faiths shall be free within the bounds of law in the exercise and performance of their religious rituals.

Article Three. No law shall contravene the tenets and provisions of the holy religion of Islam in Afghanistan.

The full text of the constitution can be found here:

(2) For articles on education see articles 43-46, in particular: Article Forty-Five. The state shall devise and implement a unified educational curricula based on the tenets of the sacred religion of Islam, national culture as well as academic principles, and develop religious subjects curricula for schools on the basis of existing Islamic sects in Afghanistan.

For religious education, see: Article Seventeen. The state shall adopt necessary measures to foster education at all levels, develop religious teachings, regulate and improve the conditions of mosques, religious schools as well as religious centers.

(3) Article Sixty-Two. The individual who becomes a presidential candidate shall have the following qualifications:

  1. Shall be a citizen of Afghanistan, Muslim, born of Afghan parents and shall not be a citizen of another country;
  2. Shall not be less than forty years old the day of candidacy;
  3. Shall not have been convicted of crimes against humanity, a criminal act or deprivation of civil rights by court.

No individual shall be elected for more than two terms as President. The provision of this article shall also apply to Vice-Presidents.

Article Sixty-Three. Before assuming office, the President shall take, in accordance with special procedures set by law, the following oath of allegiance:

“In the name of God, Most Gracious, Most Merciful, I swear by the name of God Almighty that I shall obey and protect the Holy religion of Islam, respect and supervise the implementation of the Constitution as well as other laws, safeguard the independence, national sovereignty and territorial integrity of Afghanistan, and, in seeking God Almighty’s help and support of the nation, shall exert my efforts towards the prosperity and progress of the people of Afghanistan.”

(4) Article One Hundred Thirty. In cases under consideration, the courts shall apply provisions of this Constitution as well as other laws. If there is no provision in the Constitution or other laws about a case, the courts shall, in pursuance of Hanafi jurisprudence, and, within the limits set by this Constitution, rule in a way that attains justice in the best manner.

Article One Hundred Thirty-One. The courts shall apply the Shia jurisprudence in cases involving personal matters of followers of the Shia sect in accordance with the provisions of the law. In other cases, if no clarification in this Constitution and other laws exist, the courts shall rule according to laws of this sect.

(5) Article Thirty-Five. To attain moral and material goals, the citizens of Afghanistan shall have the right to form associations in accordance with provisions of the law. The people of Afghanistan shall have the right, in accordance with provisions of the law, to form political parties, provided that:

  1. Their manifesto and charter shall not contravene the Holy religion of Islam and principles and values enshrined in this constitution;
  2. Their organizations and financial resources shall be transparent;
  3. They shall not have military or quasi-military aims and organizations; and
  4. They shall not be affiliated with foreign political parties or other sources.

Formation and operation of a party on the basis of tribalism, parochialism, language, as well as religious sectarianism shall not be permitted. A party or association formed according to provisions of the law shall not be dissolved without legal causes and the order of an authoritative court.

(6) Article One Hundred Twenty-One. At the request of the Government, or courts, the Supreme Court shall review the laws, legislative decrees, international treaties as well as international covenants for their compliance with the Constitution and their interpretation in accordance with the law.

(7) Article One Hundred Forty-Nine. The principles of adherence to the tenets of the Holy religion of Islam as well as Islamic Republicanism shall not be amended. Amending fundamental rights of the people shall be permitted only to improve them. Amending other articles of this Constitution, with due respect to new experiences and requirements of the time, as well as provisions of Articles Sixty-Seven and One Hundred Forty-Six of this Constitution, shall become effective with the proposal of the President and approval of the majority of National Assembly members.

Article One Hundred Fifty. To process the amendment proposals, a commission comprised of members of the Government, National Assembly as well as the Supreme Court shall be formed by presidential decree to prepare the draft proposal. To approve the amendment, the Loya Jirga shall be convened by a Presidential decree in accordance with the provisions of the Chapter on Loya Jirga. If the Loya Jirga approves the amendment with the majority of two thirds of its members, the President shall enforce it after endorsement.

 

 

Categories: Defence`s Feeds

Introduction to Assault Rifles

Military-Today.com - Tue, 09/04/2019 - 01:20

Introduction to Assault Rifles
Categories: Defence`s Feeds

Behold This Somehow Funny Photo Of Three Italian Typhoon Jets Escorting a Danish Seahawk Helicopter

The Aviationist Blog - Mon, 08/04/2019 - 20:23
When you have to escort a Slow Mover you may need to fly at high AOA (Angle Of Attack). The following photo was shared on social media by the Royal Danish Air Force (RDAF). It [...]
Categories: Defence`s Feeds

Minnesota ANG F-16s Join German, Polish, French, Swiss and Dutch Combat Aircraft for “Frisian Flag 2019”

The Aviationist Blog - Mon, 08/04/2019 - 15:24
Leeuwarden Air Base in The Netherlands is currently hosting the large-scale international exercise Frisian Flag 2019. Freelance photographer and reporter Edwin Schimmel visited Leeuwarden and here’s his report for The Aviationist. Frisian Flag is a [...]
Categories: Defence`s Feeds

Latest news - Next SEDE meeting - Subcommittee on Security and Defence

The dates will be confirmed after the elections to the European Parliament in May 2019.




Source : © European Union, 2019 - EP

Highlights - Study: The Scrutiny of the European Defence Fund by the EP and national parliaments - Subcommittee on Security and Defence

Since 2016, the European Union has developed a number of new initiatives on security and defence. In particular, the introduction of Permanent Structured Cooperation and the European Defence Fund have been designed to allow the EU to become a more autonomous actor with regard to crisis management, capacity building and protecting Europe and its citizens. Yet the development of these new initiatives raises questions about
their overall coherence and the role of parliamentary scrutiny. It is necessary to analyse the role of the European Parliament and national parliaments in relation to the scrutiny of the European Defence Fund. There is a need for recommendations on how parliamentary scrutiny can be enhanced at the EU level in the area of security and defence.
Further information
Full study
Source : © European Union, 2019 - EP

You Have To Watch This Crazy Cool Video Of The Last JASDF F-4EJ “OJIRO” Phantoms Of The 302nd Squadron

The Aviationist Blog - Sat, 06/04/2019 - 16:43
What an incredible footage of the 302nd Squadron Phantoms! On Mar. 19, 2019, the 302nd Squadron of the Japan Air Self Defense Force made its last flight with the F-4EJ “Kai” Phantom. The 302nd was [...]
Categories: Defence`s Feeds

EDA launches work on research prototype for cyber defence situation awareness

EDA News - Fri, 05/04/2019 - 14:12

Last week, a kick-off meeting was held at EDA to launch the contractual work on the Cyber Defence Situation Awareness Package Rapid Research Prototype (CySAP-RRP) project, in the presence of representatives of the three contributing Member States:  Spain (lead country), Germany and Italy. The industry consortium in charge of the project (INDRA Sistemas SA, Leonardo S.p.a and Fraunhofer) provided Member States with an overview of the project management plan describing tasks, milestones and project deliverables. 

The project was conceived as the first step of a spiral development in order to set up a full Cyber Situation Awareness operational capability. The CySAP-RRP will be built upon previous work done by EDA to develop a Target Architecture and System Requirements for an enhanced Cyber Defence Situation Awareness Capability. 

The core objectives of the project include essential research challenges to assist military decision-makers in cyberspace and to set the basis for a fully-fledged Command and Control (C2) system for cyber operations. 

CySAP is at the forefront of technology development with the aim of obtaining a common and standardized cyber defence planning and management functional area service. The research challenges are to provide a comprehensive understanding of the cyber defence elements in the planning and conduct phase of military operations in which cyberspace is now recognised and treated as any other domain such as land, air or maritime. 

Under the framework of EDA, the three Member States participating in CySAP agreed a common set of requirements and a Target Architecture for the capability. CySAP follows a modular approach allowing  to have a flexible set of functionalities by exercising a system engineering process. Current market available solutions for cyber situational awareness do not meet the entire spectrum of military requirements such as risk analysis, cyber related Courses of Action (CoA) development and assessment as well as support to decision-making. CySAP will provide situational analysis that can be integrated into the overall common operational picture of a mission, as a cyber information layer able to provide timely and accurate situational awareness. CySAP is set to obtain innovative solutions by joining efforts of leading defence industries and researchers in Europe.

The architectural design comprises several spirals to be completed in the next years subject to future investments. The possibility to introduce CySAP follow-on activities into PESCO or the EDIDP are currently explored and assessed. The next progress review meeting is scheduled for September 2019 in Spain. 

Background

The updated EU Capability Development Plan (CDP) endorsed by the EDA Steering Board in June 2018 reconfirmed cyber defence as a priority for capability development in the EU. The CDP recognises the need for defensive cyber operations in any operational context, based on sophisticated current and predictive cyberspace situational awareness. This includes the ability to combine large amounts of data and intelligence from numerous sources in support of rapid decision making and increased automation of the data gathering, analysis and decision-support process. 

In November 2018, the European Council adopted an updated version of the EU cyber defence policy framework (CDPF).  Supporting the development of Member States’ cyber defence capabilities is a priority area where the now established CySAP project serves as a core to guide future research and operational capabilities.

Categories: Defence`s Feeds

EDA supports NATO CCD COE ‘Locked Shields’ cyber defence exercise

EDA News - Fri, 05/04/2019 - 09:12

‘Locked Shields’, the world’s biggest and most advanced international cyber defence exercise involving life-fire attacks, is organized annually by NATO’s Cooperative Cyber Defence Centre of Excellence (CCD COE) in Tallinn. This year’s edition will take place from 9-12 April with some 1,000 experts from around 30 nations participating. EDA will support the strategic track part of the exercise.  

The exercise will see a Red team (based in Tallinn) attacking Blue Teams made up by CCD COE member states (based at exercise locations in their capitals) who will act as national rapid reaction teams deployed to assist a fictional country in handling large-scale cyber incidents and all their multiple implications. The main task of the Blue Teams is to protect and maintain their services and networks against these life attacks. Besides countering the technical attacks, information sharing, teamwork and cooperation will also be key aspects to be tested in this exercise. 

With its rich expertise and experience gained from several strategic decision-making exercises organised with Member States over recent years, EDA will support the ‘Locked Shields 2019 Strategic Track’, a parallel, table-top decision-making exercise track playing in the same fictitious, sovereign state under severe cyber-attacks from an aggressive neighbour. Participating Blue Teams will act as rapid reaction teams and advisors. High-level cyber/hybrid crisis management and legal decisions have to be made in accordance with national, EU, NATO and UN regulations by those Blue Teams. The roles of NATO, EU and UN will be played by a “White Team”, including EDA.
 

More information: 
Categories: Defence`s Feeds

Kalibr cruise missile fired from Northern Fleet port

Jane's Defense News - Fri, 05/04/2019 - 03:00
A Kalibr cruise missile has been successfully test fired for the first time from a Russian submarine moored in a port. The test launch of the Novator 3M-14 Kalibr land-attack cruise missiles from the Project 885 Yasen-class submarine Severodvinsk was reported by Russian newspaper Izvestia , citing
Categories: Defence`s Feeds

Aeronautics board approve Rafael/Stolero takeover

Jane's Defense News - Fri, 05/04/2019 - 02:00
The ILS850 million (USD237 million) acquisition of Israeli unmanned aerial vehicles (UAV) manufacturer Aeronautics by state-owned Israeli defence group Rafael and businessman Avichai Stolero has been approved by Aeronautic’s board of directors. Rafael and Stolero initially bid ILS430 million
Categories: Defence`s Feeds

Pages